03 October 2023 - The Government of Serbia has finally changed the procedure for connecting new power plants to the transmission and distribution grids
18 September 2023 - The 5,800 MW estimate is from an adequacy analysis conducted by Serbia's transmission system operator Elektromreža Srbije
10 August 2023 - The project envisages the construction of transmission infrastructure to facilitate the grid connection of new wind, and solar power plants
26 July 2023 - By changing the Law on Energy, Serbia enabled the establishment of an independent commission to oversee electricity and gas TSOs
02 June 2023 - The Government of Serbia approved a bill with changes to the Law on Energy, largely to transpose the European Union's acquis
29 May 2023 - Energy expert Nenad Jovanović created a map with the sites for power plant projects in Serbia for which grid connection requests were filed
18 May 2023 - Simulating markets will help EMS to plan short-, medium- and long-term procurement decisions, forecasting losses and investment opportunities
29 April 2023 - Minister of Mining and Energy of Serbia Dubravka Đedović said the changes to the Law on the Use of Renewable Energy Sources enable auctions
30 March 2023 - To avoid a delay in connecting their renewable power plant, investors will need to add batteries, according to the renewables bill
03 January 2023 - EMS has to secure 21.5 GWh for the operation of its substations and distribution facilities every year, and high power prices are here to stay
27 December 2022 - Slovenian and Serbian TSOs and EPEX SPOT established the first regional power exchange for Central and South-Eastern Europe
07 September 2022 - The Energy Community Secretariat opened a dispute settlement case against Serbia for failing to coordinate transmission capacity allocation with Kosovo*
09 March 2022 - Elektromreža Srbije (EMS) named Duško Aničić as its executive director for system and market operation, the Serbian business registry showed
19 January 2022 - Reacting to demands from EMS and EPS, international institutions said altering the renewable energy law in Serbia could disappoint investors
05 August 2021 - State power grid operator EMS has invested EUR 30 million in two overhead lines that will enable the integration of 2.8 GW of wind farms.
16 November 2020 - The sale of guarantees of origin for electricity produced from renewable sources in Serbia is now possible in European countries.