Without any additional investments in production capacities for secondary and tertiary frequency regulation, the electricity system in Serbia can withhold solar power plants and wind farms with a combined 5,800 MW, said Nebojša Petrović, advisor of the CEO of the country’s transmission system operator Elektromreža Srbije (EMS), at the Energy 2023 conference on Mt. Zlatibor. The domestic Energy Experts Association organized the event.

The 5,800 MW estimate is from an adequacy analysis conducted by EMS. It includes 400 MW of operational wind parks. Subtracting the 717 MW in planned facilities selected at the first auctions, 4,683 MW more solar and wind power capacity can be run within the system.

However, EMS received applications for about 19,900 MW by the end of May. By mid-September, the volume reached 21,965.2 MW. The projects are in various stages of development, and the majority are at the very beginning.

The adequacy analysis was done in line with the EU SOGL regulation, which is mandatory in the Continental Europe synchronous area

According to Petrović, the adequacy analysis was done with a probabilistic approach, required by the European Union’s System Operation Guideline (SOGL). It is mandatory in the Continental Europe synchronous area to calculate the regulation (balance) reserve when the power system has a high share of variable renewable energy sources.

“Taking all that into account, we concluded that Serbia’s electricity system, at both the transmission and distribution levels, can operate with 5,800 MW from wind parks and solar power plants with the existing regulation capacities including pumped storage hydropower plant Bajina Bašta,” Petrović said.

The analysis was part of Serbia’s ten-year transmission system development plan for the period 2023-2032

The analysis was conducted within Serbia’s ten-year transmission system development plan for 2023-2032 and under the obligation introduced by the Law on the Use of Renewable Energy Sources, adopted in late April.

The plan was submitted to the Energy Agency of the Republic of Serbia (AERS) for approval.

Petrović spoke at a panel on developing modern energy infrastructure in the context of energy storage needs. Nikola Rajaković, president of the Energy Experts Association, moderated the discussion. The participants were Maja Turković, Executive Vice President of CWP EuropeDejan Stojčevski, Chief Operating Officer of domestic electricity exchange SEEPEX, Dejan Ostojić, member of the Supervisory Board of state-owned coal and power producer Elektroprivreda Srbije (EPS), and energy expert Željko Marković.

Applicants are awaiting the regulation on the conditions of electricity delivery and supply

Petrović said EMS received requests for the connection of power plants with a capacity of 4,500 MW in line with the old Law on Energy, until April 2021, compared to 1,000 MW in applications sent to distribution system operator Elektrodistribucija Srbije (EDS).

Together, it roughly represents the capacity from the adequacy analysis, he added and explained that a large part is advanced projects.

The remaining applicants await the adoption of a new regulation on the conditions of electricity delivery and supply, Petrović stressed.

In his words, the analysis demonstrates no hurdles regarding grid stability for the construction and connection of all power plants for which connection applications were filed in line with the old Law on Energy.

He noted that the Law on the Use of Renewable Energy Sources makes it possible for a developer to avoid delaying a grid connection for a wind or solar power project by providing additional secondary reserve capacity as an auxiliary service.

The capacity will be offered to the transmission system operator, EMS, for system services of secondary frequency regulation and capacity exchange.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

croatia wind farm cemernica vsb totalenergies

TotalEnergies developing 80 MW Čemernica wind farm in Croatia

10 April 2026 - The Čemernica wind farm is planned to be built in the municipality of Dicmo and the city of Trilj, near the coastal city of Split

eu first cbam certificate price european commission

European Commission sets first CBAM certificate price

10 April 2026 - The European Commission has published the first price of CBAM certificates for 2026 Q1 on its new dedicated page on the CBAM website

Serbia’s Đedović Handanović in Azerbaijan for discussions on gas projects

08 April 2026 - Serbian Minister Dubravka Đedović Handanović met in Baku with Azerbaijani ministers and the head of SOCAR

croatia rimac technology new bmw i7 sedan battery

BMW, Rimac to unveil fully electric i7 on April 22

08 April 2026 - The new BMW i7 will be the first BMW Group BEV to feature a jointly developed battery system, manufactured at the Rimac Campus near Zagreb