Serbia and Romania power interconnector near completion

Photo: Pixabay

Published

October 31, 2017

Comments

comments icon

0

Share

Published:

October 31, 2017

Comments:

comments icon

0

Share

The Resita-Pančevo transmission line construction between Romania and Serbia is getting closer to the end. The role of the interconnection between two countries is of strengthening national electricity systems as well as the South-East European one.

Romania’s national electricity transmission company, Transelectrica announced that it completed the crossing of the border to Serbia with the 400 kV Resita (Romania) – Pancevo (Serbia) transmission line. This is one of the final stages in the realization of the interconnection project on the Romania-Serbia relationship, according to energynomics.

The 400 kV Resita-Pancevo is a project of common interest at European level. It will allow also the elimination of major congestions in the Romanian and Serbian power systems as well as the increase of the transfer capacity between two countries and across the South-Eastern Europe.

“I am glad we have been able to unlock this important project for Transelectrica, in recent months. The works at the Resita-Pancevo line have a high level of complexity and engage specialists from many fields. In the West [of Romania], there is a major project – Mid Continental East Corridor – which contributes crucially to the strategic priorities of the European Union for trans-European energy infrastructure. The Resita – Pancevo line is part of this project, but also of ours, and of the Government’s strategy of closing the 400 kV ring”, said Corina Popescu, CEO of Transelectrica, according to The Diplomat.

Construction of the Serbian section of the overhead power line towards Reșița in Romania started at Pančevo substation northeast of capital Belgrade, in early 2016. The project worth EUR 24.7 million was planned to be completed by the end of this year for the trial run, the transmission system operator Elektromreža Srbije (EMS) announced back then.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

EVN Macedonia BESS 10 MW into operation at solar park

EVN Macedonia puts BESS of 10 MW into operation at its solar park

13 May 2026 - EVN Macedonia commissioned a battery energy storage system within its Probištip photovoltaic plant in North Macedonia

Energy companies confront dual mandate keeping supply secure while accelerating green transition BEF 2026

Energy companies in Western Balkans confront dual mandate – keeping supply secure while accelerating green transition

13 May 2026 - Companies in the region have challenges in energy security, decarbonization and digitalization, and the key is investing in production, the grid and batteries, according to the panel on power system transition at Belgrade Energy Forum 2026

serbia eu region bef 2026 ivan asanovic cges market coupling

Asanović: Montenegro expects European Commission to clear market coupling by end-June

12 May 2026 - Ivan Asanović, CEO of Montenegro's transmission system operator, participated in the panel on transmission grid development at BEF 2026

serbia eu region bef 2026 jelena matejic ems renewables grid connection

Matejić: Serbia’s grid to integrate 12 GW of renewables in next six years

12 May 2026 - Jelena Matejić, General Manager of Elektromreža Srbije, took part in a panel on transmission grids at Belgrade Energy Forum 2026