Serbia and Romania power interconnector near completion

Photo: Pixabay

Published

October 31, 2017

Comments

comments icon

0

Share

Published:

October 31, 2017

Comments:

comments icon

0

Share

The Resita-Pančevo transmission line construction between Romania and Serbia is getting closer to the end. The role of the interconnection between two countries is of strengthening national electricity systems as well as the South-East European one.

Romania’s national electricity transmission company, Transelectrica announced that it completed the crossing of the border to Serbia with the 400 kV Resita (Romania) – Pancevo (Serbia) transmission line. This is one of the final stages in the realization of the interconnection project on the Romania-Serbia relationship, according to energynomics.

The 400 kV Resita-Pancevo is a project of common interest at European level. It will allow also the elimination of major congestions in the Romanian and Serbian power systems as well as the increase of the transfer capacity between two countries and across the South-Eastern Europe.

“I am glad we have been able to unlock this important project for Transelectrica, in recent months. The works at the Resita-Pancevo line have a high level of complexity and engage specialists from many fields. In the West [of Romania], there is a major project – Mid Continental East Corridor – which contributes crucially to the strategic priorities of the European Union for trans-European energy infrastructure. The Resita – Pancevo line is part of this project, but also of ours, and of the Government’s strategy of closing the 400 kV ring”, said Corina Popescu, CEO of Transelectrica, according to The Diplomat.

Construction of the Serbian section of the overhead power line towards Reșița in Romania started at Pančevo substation northeast of capital Belgrade, in early 2016. The project worth EUR 24.7 million was planned to be completed by the end of this year for the trial run, the transmission system operator Elektromreža Srbije (EMS) announced back then.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

bih first energy community visoko bihrec serda

Visoko set to host BiH’s first energy community

11 March 2026 - The Sarajevo Economic Region Development Agency has signed the implementation agreement for the first phase of the BIHREC project

There is no power price crisis in Europe analysis

There is no power price crisis in Europe – analysis

11 March 2026 - Intervening in wholesale electricity markets would increase costs for consumers, while undermining investor confidence, according to a paper that Eurelectric commissioned

RGreen Renalfa Solarpro start another joint venture for Romania Poland

RGreen, Renalfa Solarpro start another joint venture for Romania, Poland

11 March 2026 - RGreen Invest and Renalfa Solarpro Group are establishing one more joint venture company – Renalfa Power Clusters (RPC)

HELLENiQ Energy first PV plants in Romania online

HELLENiQ Energy gets its first PV plants in Romania online

11 March 2026 - Athens-based conglomerate HELLENiQ Energy started commercial operations of its first two photovoltaic parks in Romania