Serbia and Romania power interconnector near completion

Photo: Pixabay

Published

October 31, 2017

Comments

comments icon

0

Share

Published:

October 31, 2017

Comments:

comments icon

0

Share

The Resita-Pančevo transmission line construction between Romania and Serbia is getting closer to the end. The role of the interconnection between two countries is of strengthening national electricity systems as well as the South-East European one.

Romania’s national electricity transmission company, Transelectrica announced that it completed the crossing of the border to Serbia with the 400 kV Resita (Romania) – Pancevo (Serbia) transmission line. This is one of the final stages in the realization of the interconnection project on the Romania-Serbia relationship, according to energynomics.

The 400 kV Resita-Pancevo is a project of common interest at European level. It will allow also the elimination of major congestions in the Romanian and Serbian power systems as well as the increase of the transfer capacity between two countries and across the South-Eastern Europe.

“I am glad we have been able to unlock this important project for Transelectrica, in recent months. The works at the Resita-Pancevo line have a high level of complexity and engage specialists from many fields. In the West [of Romania], there is a major project – Mid Continental East Corridor – which contributes crucially to the strategic priorities of the European Union for trans-European energy infrastructure. The Resita – Pancevo line is part of this project, but also of ours, and of the Government’s strategy of closing the 400 kV ring”, said Corina Popescu, CEO of Transelectrica, according to The Diplomat.

Construction of the Serbian section of the overhead power line towards Reșița in Romania started at Pančevo substation northeast of capital Belgrade, in early 2016. The project worth EUR 24.7 million was planned to be completed by the end of this year for the trial run, the transmission system operator Elektromreža Srbije (EMS) announced back then.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

romania ppc bess battery salbatica wind farm

PPC to install 60 MWh battery system at Sălbatica wind farm

11 February 2026 - PPC operates the Sălbatica 1 and Sălbatica 2 wind farms, with a combined capacity of 140 MW, located in Tulcea County

Next generation geothermal challenging competitiveness gas power plants

Next generation geothermal challenging competitiveness of gas power plants

11 February 2026 - With its new solutions and falling costs, geothermal power can already replace 42% of EU coal- and gas-fired plant output, Ember found

El Mor advances delivery ready BESS projects Romania

El-Mor advances delivery-ready BESS projects in Romania

11 February 2026 - El-Mor Electric Installations & Services is advancing two large stand-alone BESS projects in Romania

north macedonia solar memo power exchange analysis ana angelova

Solar power production driving prices on North Macedonia’s power exchange

10 February 2026 - Ana Angelova, a market operations specialist at the National Electricity Market Operator, analyzed official power exchange data for 2024