Romania loses arbitration versus investors in solar power

Romania loses arbitration versus investors in solar power

Photo: Franz W. from Pixabay

Published

October 25, 2022

Country

Comments

comments icon

0

Share

Published:

October 25, 2022

Country:

Comments:

comments icon

0

Share

A tribunal operating under the World Bank has ruled in favor of ten companies that initiated arbitration with the argument that Romania violated the Energy Charter Treaty by lowering incentives for their solar power plants.

Romania was supposed to compensate investors when it altered its rules on incentives for renewable energy production, according to an arbitration panel at the International Centre for Settlement of Investment Disputes – ICSID. Ten companies from Austria, the Netherlands, Germany and Cyprus launched a case in 2018 under the Energy Charter Treaty (ECT) and the ICSID Convention.

They built five solar power plants. The investors, led by LSG Group from Austria, argued that they were encouraged to invest in the country but that changes in 2013, 2014, 2017 and 2018 caused them losses in relation to their business plans.

The decision is not yet final, but the two sides were asked to negotiate on rightful compensation. ICSID was founded in 1996. It operates under the World Bank.

Changes in regulations were too drastic

Romania claimed it did not commit to never changing the legislation and said it was necessary to reduce overcompensation and limit the increase in electricity prices for consumers. The tribunal pointed out, citing the Energy Charter Treaty, that the changes were too drastic.

The Ministry of Energy said it doesn’t expect new lawsuits in relation to the ruling.

Romania introduced a green certificate scheme in 2008 for electricity from renewable sources. Investors were entitled to six green certificates per megawatt-hour that suppliers were obligated to buy, so producers would receive an extra EUR 162 per MWh to EUR 330 per MWh by trading within the mechanism.

Electricity costs were threatening to sink Romanian industry

In 2013, the government cut the number of green certificates to four per megawatt-hour and delayed the payment for the rest to between 2025 and 2030. Romania altered the rules with the argument that the price of solar power equipment dropped sharply and that the industry was suffering under the high cost of the green certificates.

Of note, French President Emmanuel Macron said last week that his country would withdraw from the Energy Charter Treaty. Spain, the Netherlands and Poland earlier made similar decisions. Investors have been launching cases against host countries as their governments canceled energy projects and introduced stricter environmental rules to comply with the Paris Agreement on climate change.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

world bank prosumers solar financing republic of srpska

World Bank could finance 20,000 prosumers in Republic of Srpska

23 February 2026 - The World Bank intends to provide a loan for a prosumer project in the Republic of Srpska, with a financing decision expected as early as May

world ppa bloombergnef report 2025

Global clean PPA market shrinks for first time in nearly one decade

23 February 2026 - Tech giants contracted almost half of the total volume, and firm power deals are set to become dominant, according to a BloombergNEF report

Saudi Acwa USD 5 billion renewables investment Turkey

Saudi’s Acwa starts USD 5 billion renewables investment in Turkey

23 February 2026 - Saudi Arabian energy utility Acwa agreed to build two photovoltaic plants in Turkey, of 1 GW each. It is the first phase of a 5 GW plan.

Serbia to prepare by 2032 for nuclear plant construction Russia possible partner

Serbia to prepare by 2032 for nuclear plant construction – Russia possible partner

23 February 2026 - Serbia is building its nuclear program with EDF for a 2032 launch, but remains open to other partners like Rosatom