Romania loses arbitration versus investors in solar power

Romania loses arbitration versus investors in solar power

Photo: Franz W. from Pixabay

Published

October 25, 2022

Country

Comments

comments icon

0

Share

Published:

October 25, 2022

Country:

Comments:

comments icon

0

Share

A tribunal operating under the World Bank has ruled in favor of ten companies that initiated arbitration with the argument that Romania violated the Energy Charter Treaty by lowering incentives for their solar power plants.

Romania was supposed to compensate investors when it altered its rules on incentives for renewable energy production, according to an arbitration panel at the International Centre for Settlement of Investment Disputes – ICSID. Ten companies from Austria, the Netherlands, Germany and Cyprus launched a case in 2018 under the Energy Charter Treaty (ECT) and the ICSID Convention.

They built five solar power plants. The investors, led by LSG Group from Austria, argued that they were encouraged to invest in the country but that changes in 2013, 2014, 2017 and 2018 caused them losses in relation to their business plans.

The decision is not yet final, but the two sides were asked to negotiate on rightful compensation. ICSID was founded in 1996. It operates under the World Bank.

Changes in regulations were too drastic

Romania claimed it did not commit to never changing the legislation and said it was necessary to reduce overcompensation and limit the increase in electricity prices for consumers. The tribunal pointed out, citing the Energy Charter Treaty, that the changes were too drastic.

The Ministry of Energy said it doesn’t expect new lawsuits in relation to the ruling.

Romania introduced a green certificate scheme in 2008 for electricity from renewable sources. Investors were entitled to six green certificates per megawatt-hour that suppliers were obligated to buy, so producers would receive an extra EUR 162 per MWh to EUR 330 per MWh by trading within the mechanism.

Electricity costs were threatening to sink Romanian industry

In 2013, the government cut the number of green certificates to four per megawatt-hour and delayed the payment for the rest to between 2025 and 2030. Romania altered the rules with the argument that the price of solar power equipment dropped sharply and that the industry was suffering under the high cost of the green certificates.

Of note, French President Emmanuel Macron said last week that his country would withdraw from the Energy Charter Treaty. Spain, the Netherlands and Poland earlier made similar decisions. Investors have been launching cases against host countries as their governments canceled energy projects and introduced stricter environmental rules to comply with the Paris Agreement on climate change.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

ems ai transmission

EMS plans to use AI in construction approvals

21 November 2024 - EMS has decided to automate its construction approval procedure by introducing state-of-the-art AI solutions

IPTO ENCS cybersecurity grid

Greece’s IPTO joins European Network for Cyber Security

21 November 2024 - The European Network for Cyber Security (ENCS) has announced that IPTO has officially joined the network as a full member

montenegro gvozd epcg nordex agreement

Montenegro’s power utility EPCG begins construction of Gvozd wind farm

21 November 2024 - Wind farm Gvozd will be the first large-scale power generation facility to be built by EPCG in more than 40 years

Bulgarian waterworks firm installs in pipe hydropower generator

Bulgarian waterworks firm installs in-pipe hydropower generator

21 November 2024 - A waterworks and sewerage firm in Bulgaria produces electricity using an in-pipe hydropower device in a supply line