Renewables in Greece get shortcut to grid connection with PPAs

Renewables-Greece-get-shortcut-grid-connection-PPAs

Photo: iStock

Published

April 23, 2024

Country

Comments

comments icon

0

Share

Published:

April 23, 2024

Country:

Comments:

comments icon

0

Share

Renewable electricity projects in Greece that have power purchase agreements signed with energy-intensive industrial consumers can skip the line for final connection offers from the Independent Power Transmission Operator.

Developers of green power plant projects in Greece applied with their power purchase agreements – PPAs for an overall 3.8 GW to get grid connection priority, Energypress learned from unnamed sources. The government directive includes the possibility of lowering the capacity by 20% so that more facilities come online. It translates to slightly over 3 GW with a possibility to be fast-tracked.

IPTO seen issuing final offers for 1.5 GW

The priority clause is envisaged for PPAs with domestic energy-intensive industrial producers as well as power plants for agricultural purposes. The round was closed on April 16.

Still, the total portfolio planned for supplying the industry that would get final connection offers from the Independent Power Transmission Operator (IPTO or, in Greek, Admie) is likely to be lower, the article adds. The media outlet’s market sources estimated it at 2 GW. The Ministry of Environment and Energy is expected to issue a decision that 1.5 GW would bypass the regular procedure, the news website added.

One of the conditions is for the offtaker to submit a report on its annual electricity consumption over the previous three years. The idea is to cut energy costs as soon as possible.

PPC has 820 MW of solar power closest to shortcut

The report points to the solar PPAs that government-controlled Public Power Corp. (PPC) signed with metals conglomerate Viohalco and  Titan Cement as the first in line for the grid connection approval. The initial bilateral contracts, for 520 MW and 300 MW, respectively, are said to have been recently renegotiated.

Developers adjusted some other submitted PPAs to include a consumer if they originally agreed them only with a supplier, according to the Greek media. The changes reportedly included price cuts.

IPTO’s April report showed that operational power plants reached 13.1 GW in combined capacity, of which 5.4 GW is in its transmission network and the rest on the distribution level. Together with projects that obtained final grid connection offers, the sums are 28.5 GW and 19.2 GW, respectively. The total is already 5 GW higher than the target in the National Energy and Climate Plan.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

koncar substation sweden contract

Končar lands new record substation deal

16 April 2026 - Croatian engineering firm Končar has signed a EUR 24 million contract to build a substation...

Parliamentarians Energy Community energy security with MEPs Brussels

Parliamentarians from Energy Community discuss energy security with MEPs in Brussels

16 April 2026 - In focus at the Energy Community Parliamentary Plenum in Brussels was the mutual need to integrate energy markets to protect against price and security of supply shocks

china envision world largest wind solar project

Envision inaugurates world’s largest wind-solar power plant

16 April 2026 - In February, the China-based company commissioned the world’s largest single-site battery energy storage system

Bulgaria ten sites pumped storage hydropower plants repairs Chaira unit

Bulgaria finds ten sites for pumped storage hydropower plants, repairs another Chaira unit

16 April 2026 - Two units in the Chaira system in Bulgaria are functional again, while the government is planning ten pumped storage hydropower projects