Project underway for 99 MW Bokšić solar plant with battery storage

boksic solar power plant battery

Photo: Pexels

Published

July 3, 2025

Country

Comments

comments icon

0

Share

Published:

July 3, 2025

Country:

Comments:

comments icon

0

Share

The Croatian Ministry of Environmental Protection and Green Transition has initiated a procedure to determine the need for an environmental impact assessment for the planned 99 MW solar power project Bokšić, which includes a battery energy storage system.

The annual electricity production of the Bokšić solar power plant is estimated at just under 120 GWh. The facility, with a planned connection power of 89 MW, would be connected to the grid through a new 110/33 kV transformer station, and then to the existing 110 kV Našice-Slatina transmission line.

The annual electricity output is estimated at just under 120 GWh

The project also includes a battery energy storage system (BESS), according to the environmental impact assessment report prepared in February and updated in June. It would be designed for an operating power of 38 MW and a capacity of 70.8 MWh, with an expected lifespan of 20 years.

Solar power plant Bokšić will have a 70.8 MWh battery system

The assessment procedure is necessary because the developer, Zagreb-based Funicula, intends to build a stand-alone photovoltaic plant, according to the ministry. The project’s site is near Bokšić, in the Đurđenovac municipality in Osijek-Baranja County.

The solar power plant is planned to occupy ​​about 123.8 hectares of land, with photovoltaic panels covering about 46 hectares. The site will be enclosed by a protective masonry fence up to two meters high, raised at least 15 centimeters above the ground to allow small animals to pass underneath, according to the ministry.

Bokšić is among the largest solar projects in Croatia

Few solar projects in Croatia are for a larger capacity than Bokšić. State power utility Hrvatska elektroprivreda (HEP) is working on the Korlat endeavor, also of 99 MW. At an auction last year, two major solar power projects were awarded market premiums – Promina, with a planned installed capacity of around 189 MW, developed by Spain-based Acciona Energia, and Obrovac Sinjski, for 144 MW, to be built by Aurelis Solis.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

croatia hep koncar hpp varazdin contract

Croatia’s HEP to invest EUR 157 million in HPP Varaždin

19 January 2026 - HEP and Končar have signed a contract for the reconstruction of the generating units at the Varaždin hydropower plant

IRENA Global daily flexibility needs are quadrupling by 2050

IRENA: Global daily flexibility needs are quadrupling by 2050

19 January 2026 - IRENA expects the world's electricity system flexibility needs, on a daily timescale, to quadruple by 2050 from the 2019 level

Bulgaria host renewable electricity plants on Luxembourg s behalf

Bulgaria to host renewable electricity plants on Luxembourg’s behalf

16 January 2026 - Bulgaria joined Finland as a host country for renewables projects funded by Luxembourg, under the RENEWFM program for 2026

Renewables account 99 Turkey net electricity capacity additions

Renewables account for 99% of Turkey’s net electricity capacity additions

16 January 2026 - Electricity capacity in Turkey reached 122 GW in 2025, of which 62% was from renewables, according to the SHURA Energy Transition Center