Greece needs 7 GW of energy storage by 2030 to avoid high curtailments

Greece will need 7 GW of storage by 2030 to avoid high curtailments

Photo: Freepik

Published

July 27, 2024

Country

Comments

comments icon

0

Share

Published:

July 27, 2024

Country:

Comments:

comments icon

0

Share

Up to 20% of renewable electricity production is expected to be curtailed by 2030 in Greece if no new investments are made in energy storage.

Greece is faced with ever-increasing curtailments of renewable energy production. Based on expectations from the revised National Energy and Climate Plan (NECP), an attempt will be made to deal with the issue by encouraging investment in storage.

Curtailments are projected to reach 5% of green energy production by the end of 2024 and increase further to 10% in the following year, according to participants at a recent webinar organized by the Hellenic Association of Photovoltaic Companies (HELAPCO).

The Green Tank said that in absolute terms they have increased from 308 GWh in the first four months of the year to 515 GWh through July. Despite the rise of demand in the summer season, 85 GWh still had to be curtailed in June and July.

It creates a problem not just for renewable energy producers, but also for consumers, who need every cheap electron coming from wind and solar farms to reduce their costs.

Photovoltaics would face 20% curtailments without batteries

Professor Pantelis Biskas from the Aristotle University of Thessaloniki (AUTH) estimates that by 2030 curtailments will affect 15% to 16% of wind power capacity and 20% of photovoltaics.

Revised NECP to set storage goal

The obvious solution is energy storage and the revised NECP is expected to provide visibility for more investments. Biskas said storage must reach 7 GW to 8 GW by 2030 to reduce curtailments to just 2% to 4% and keep energy costs low for consumers. The system requires both batteries and pumped storage hydropower plants.

The exact goal for storage in the final NECP is not yet known. The plan is expected to be submitted for public consultation within the next few weeks by the Ministry of Environment and Energy.

It should be added that Greece has already moved forward with its first 1,000 MW of battery storage systems. So far two auctions have taken place successfully and the first projects are expected to be completed in 2025.

The ministry is still preparing Greece’s third subsidy auction for standalone batteries. The deadline for submissions should apparently be set for early September. Facilities with a four-hour duration can qualify, while the requirement was two hours in the first two rounds. The quota would be 300 MW.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Bulgaria suspends ill designed solar energy support program

Bulgaria suspends ill-designed solar energy support program

14 April 2025 - In a suspended scheme for solar thermal collectors and PV panels, beneficiaries need to buy and install them, and then they get reimbursed

Romania Hidroelectrica contractors 36 MW battery system only wind farm Crucea Nord

Romania’s Hidroelectrica picks contractors for 36 MW battery system at its only wind farm

14 April 2025 - Prime Batteries Technology and Enevo Group won Hidroelectrica's tender for the installation of a battery energy storage system of 36 MW

Turkey renewables failing cover power demand growth despite solar boom

Turkey’s renewables failing to cover power demand growth despite solar boom

14 April 2025 - Turkey became a net electricity exporter in 2024, but wind and solar are still not growing fast enough to meet rising domestic power demand

JC_HE on the wall_resized

Europe must finance its clean future now

14 April 2025 - Europe must accelerate investment and action on clean hydrogen to secure its leadership in the global energy transition and avoid falling behind.