Feasibility Study Conclusions on a Regional 400 kV Electricity Interconnection

Published

April 10, 2015

Country

Comments

comments icon

0

Share

Published:

April 10, 2015

Country:

Comments:

comments icon

0

Share

The Feasibility Study for the 400 kV Interconnection between Serbia, Montenegro, and Bosnia and Herzegovina has recently been completed, with the cooperation of the electricity system operators in all three countries (EMS, CGES, NOS and Elektroprenos) and the financial support of the European Commission under the WBIF Infrastructure Projects Facility, as well as that of the European Bank for Reconstruction and Development (EBRD) – a prospective financier of the project, according to the press release published on WBIF’s website.

The study investigated the development of a planned interconnection of 400kV amongst Bajina Basta in Serbia, Pljevlja in Montenegro and Visegrad in Bosnia and Herzegovina. The study has analyzed all aspects of the proposed interconnection, (technical, legal and regulatory, economic, market, social etc.) and has demonstrated the project’s feasibility and viability.

The findings of the environmental and social impact assessment (ESIA) indicate that this project can be developed and implemented with little or no disturbance to the environment and to the people who live and work in its surrounding area.

The connection is included in the list of priority projects supported by the Energy Community Secretariat in Vienna as well as in the European Electricity Transmission System Operators Association’s (ENTSO-e) ten-year network development plans for the SEE region.

In the broader context, when this project is complete, it will be part of a strong electricity transmission corridor between Central Serbia and Italy, via the planned undersea cable between Montenegro and Italy.

It is also linked to the previously completed WBIF-funded Feasibility Study on the Western Serbia upgrade (connection between Obrenovac and Bajina Basta) and the Lastva – Pljevlja Feasibility Study in Montenegro, which is now under construction.

Serbia and Montenegro have already taken necessary steps for the completion of this Interconnection by submitting to the WBIF a new joint application for the financing of the detailed design and tender documents associated with the construction works.

Tags: , ,

Related Articles

Greece 50 support businesses batteries

Greece to provide up to 50% support to businesses for batteries

23 December 2024 - The Greek Ministry of Environment and Energy launched the Energy Storage for Businesses program with subsidies for installing batteries

Borislav Kostadinov Green for Growth Fund accelerating expansion GGF EUR 1 billion mark interview

Kostadinov: The Green for Growth Fund is accelerating its expansion after topping EUR 1 billion mark

23 December 2024 - The Green for Growth Fund recently topped EUR 1 billion in AUM and the demand for its offering is steadily picking up, the Director for GGF at Finance in Motion Borislav Kostadinov revealed

DRI OMV Petrom Romania largest physical PPA

DRI, OMV Petrom sign Romania’s largest physical PPA so far

21 December 2024 - The new physical solar power purchase agreement between DRI and OMV Petrom is the largest ever in Romania

Renewable energy project frenzy in Greece defies curtailments, grid constraints

Renewable energy project frenzy in Greece defies curtailments

20 December 2024 - Applications for new renewable energy projects continued unabated in Greece in 2024 according to Independent Power Transmission Operator