Energy Community mediates dispute between state, HPP Energji Ashta

Photo: Energji Ashta

Published

September 26, 2018

Country

Comments

comments icon

0

Share

Published:

September 26, 2018

Country:

Comments:

comments icon

0

Share

The Energy Community Secretariat’s Dispute Resolution and Negotiation Centre has organized the first meetings with the parties and all other entities involved in the dispute related to balancing issues in the Albanian hydro sector, the Energy Community Secretariat has said in a press release.

The parties involved are the Ministry of Infrastructure and Energy of Albania and the Energji Ashta hydropower plant (HPP), owned by power companies Verbund and EVN.

The dispute arose between KESH, the largest electricity producer in Albania, and HPP Energji Ashta, and it involves other Albanian state-owned stakeholders: ERE, the energy regulator in Albania, the Albanian distribution system operator OSHEE, and the Albanian transmission system operator OST, the Secretariat said.

A dispute between the private and the state company was brought to the Secretariat’s attention earlier last year.

Dirk Buschle, Head of the Legal Unit and Deputy Director of the Secretariat, has been appointed as mediator, and he is supported by Rozeta Karova and Arben Kllokoqi.

The Energy Community Secretariat’s Dispute Resolution and Negotiation Centre was established in 2016 as a response to signals that the settlement alternatives currently available for energy disputes no longer respond to the needs of national authorities and stakeholders.

Joint venture by Verbund and EVN

HPP Energji Ashta, operated by a joint-venture by Austrian power companies Verbund and EVN, was commissioned under an investment worth EUR 200 million. It started electricity production in June 2012 while the concession contract was signed for a period of 35 years. At the end of the 35-year concession, the HPP will be handed over to the Republic of Albania.

This run-of-river HPP is located in the north of Albania on the Drin river with an installed capacity of 53 MW and annual production of 242 GWh. The generated electricity is delivered to state-owned power utility KESH. The PPA agreement was signed on 15 years.

Verbund and EVN are majority owned by the Austrian state. Verbund is the largest electricity producer in this country, while EVN is the second-largest power company.

A week ago Romania’s power producer Hidroelectrica announced plans to sign cooperation agreement with Verbund.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

world energy crisis war renewables boom Simon Stiell un

Energy crisis fueled by Iran war makes economic logic of renewables impossible to ignore

04 May 2026 - The energy crisis fueled by the Iran war has made the economic logic of renewables impossible to ignore, according to Simon Stiell

Premier Energy building one of largest battery systems in Southeastern Europe

Premier Energy building one of largest battery systems in Southeastern Europe

04 May 2026 - Premier Energy Group has begun the construction of a 200 MW / 400 MWh battery energy storage system (BESS) in eastern Romania

nuclearelectrica us exim loan cernavoda expansion_cr

US export bank signs USD 57.3 million loan to back Romania’s nuclear plant expansion

04 May 2026 - The Export-Import Bank of the United States has signed a loan for engineering and project management services for two new reactors at the Cernavodă plant

energy community regulatory board evaluation report peci list projects

Six Projects of Energy Community Interest advancing without systemic delays

04 May 2026 - The Evaluation Report on PECI is providing an overview of the implementation progress of projects included in the 2024 PECI list