El-Mor advances delivery-ready BESS projects in Romania

El Mor advances delivery ready BESS projects Romania

Photo: El-Mor

Published

February 11, 2026

Country

Comments

comments icon

0

Share

Published:

February 11, 2026

Country:

Comments:

comments icon

0

Share

Romania’s grid-scale energy storage market is moving quickly from development to execution, and time-to-market is emerging as the key differentiator. Against this backdrop, El-Mor Electric Installations & Services is advancing two large stand-alone Battery Energy Storage System (BESS) projects designed for rapid delivery: BRADU BESS (Argeș) and BRAZI BESS (Prahova).

Each project targets 203 MW with up to 800 MWh of energy capacity (4-hour duration) and is planned to connect at 110 kV to substations operated by Romania’s transmission system operator, Transelectrica. Both already hold an ATR (technical connection approval) and are on track for full RTB (ready-to-build) in Q1 2026, with a clear pathway toward commissioning in H1 2027, subject to investor execution and financing.

As Romania’s BESS market quickly expands and evolves from speculative development to “delivery phase,” many projects may appear similar at first glance. What increasingly separates bankable opportunities from speculative pipelines is execution certainty: connection clarity, mature permits, optimized connection CAPEX, and documentation that can withstand lender-grade due diligence.

El-Mor’s development approach is built around de-risking the elements that typically delay BESS projects – particularly the grid interface and permitting quality – so an investor can move fast with fewer late-stage surprises.

Quality control, risk management, bankability

El-Mor Electric Installations & Services is a public company listed on the Tel Aviv Stock Exchange, reporting over €200 million in 2025 sales. Through its PV and BESS project activity, the company emphasizes an engineering-led approach and decades of high-voltage experience, underpinning a development practice focused on quality control, risk management, and overall bankability of each permitting package.

A core theme in El-Mor’s development approach is technology flexibility. The projects are permitted on an equipment-agnostic basis, allowing an investor to select BESS containers and Power Conversion System (PCS) technology at the detailed design phase. This matters because equipment availability, pricing, and lender bankability requirements can shift, and a project able to adapt without reopening permits is better positioned to preserve schedule.

Second project due for construction start before end-March

BRADU BESS is a 203 MW / up to 800 MWh project in Bradu commune (Argeș), connecting to Transelectrica’s BRADU 400/220/110 kV substation. Its underground 110 kV cable route is approximately 0.6 km, supporting both schedule and connection cost optimization. El-Mor notes that building permits were issued in January 2026, with GCA (Grid Connection Agreement) signature targeted for March 2026.

BRAZI BESS is a 203 MW / up to 800 MWh project in Brazi commune (Prahova), planned to connect to Transelectrica’s BRAZI 400/220/110 kV substation via an underground 110 kV cable route of approximately 1.2 km. Development was initiated in 2023, and the project is on track for full RTB in Q1 2026.

In a market where speed of execution and certainty have become essential investment criteria, “delivery-ready” only matters if it survives rigorous due diligence. El-Mor’s positioning emphasizes disciplined VDR management and a permitting package engineered to keep options open while enabling fast execution.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

El Mor advances delivery ready BESS projects Romania

El-Mor advances delivery-ready BESS projects in Romania

11 February 2026 - El-Mor Electric Installations & Services is advancing two large stand-alone BESS projects in Romania

north macedonia solar memo power exchange analysis ana angelova

Solar power production driving prices on North Macedonia’s power exchange

10 February 2026 - Ana Angelova, a market operations specialist at the National Electricity Market Operator, analyzed official power exchange data for 2024

envision battery system china

China-based Envision launches world’s largest battery energy storage system

10 February 2026 - The 4 GWh project marks the completion and grid connection of Envision's 12.8 GWh battery energy storage cluster in northern China

First car with sodium ion batteries entering mass production

First car with sodium ion batteries entering mass production

10 February 2026 - Changan presented the world's first mass-produced passenger vehicle equipped with sodium ion batteries, in partnership with CATL