Clean-up process underway for idle permits

Published

June 10, 2015

Comments

comments icon

0

Share

Published:

June 10, 2015

Comments:

comments icon

0

Share

Procedures are underway for clearing a backlog of renewable energy source permits issued for projects that now stand no chance of being actualized, Energy Press portal said. Idle applications are being eliminated through a process based on legislation that demands banking guarantees worth the equivalent of respective projects from applicants.

At the same time, Hedno (Hellenic Electricity Distribution Network Operator) has launched a clean-up mission of its own for roof-mounted photovoltaic systems. It is preparing to give older applicants one month to resubmit their applications as a sign of genuine interest. Otherwise, their applications will be shelved to make way for a new wave of interest being expressed by individuals and enterprises seeking to capitalize on a newly introduced net metering legal framework, the report said. The net metering plan will enable electricity consumers who generate their own power from an eligible on-site facility and deliver it to local distribution facilities, to offset the electric energy provided by the utility during an applicable billing period.

A total of 1,665 applications for roof-mounted photovoltaic systems with a total capacity of 14.32 MW had been submitted until the end of September 2013, the most recent date for which Hedno’s data is available. The older applications for household photovoltaic systems, now sitting idly and saturating capacity limits, are blocking entrepreneurial photovoltaic interest on islands with major tourism activity, the Energypress.eu report said.

Meanwhile, despite promising energy cost-cutting benefits for the agricultural sector, as has been pointed out by specialized studies, the implementation of photovoltaic systems through net metering procedures is being obstructed by law. A legislative amendment made in 2011 does not permit photovoltaic system installations for land placed under a high-productivity category. The amendment, made to settle issues concerning land transfers in high-production areas, unintentionally affected the sector.

Related Articles

El Mor advances delivery ready BESS projects Romania

El-Mor advances delivery-ready BESS projects in Romania

11 February 2026 - El-Mor Electric Installations & Services is advancing two large stand-alone BESS projects in Romania

north macedonia grants green businesses inova

North Macedonia launches EUR 22 million grant scheme for green businesses

10 February 2026 - The project for supporting green businesses with grants until 2030 is worth EUR 25 million, of which EUR 22 million is for the subsidies

north macedonia solar memo power exchange analysis ana angelova

Solar power production driving prices on North Macedonia’s power exchange

10 February 2026 - Ana Angelova, a market operations specialist at the National Electricity Market Operator, analyzed official power exchange data for 2024

envision battery system china

China-based Envision launches world’s largest battery energy storage system

10 February 2026 - The 4 GWh project marks the completion and grid connection of Envision's 12.8 GWh battery energy storage cluster in northern China