Burdur solar park gets online in record time

Published

December 1, 2015

Comments

comments icon

0

Share

Published:

December 1, 2015

Comments:

comments icon

0

Share

Hanwha Q Cells Turkey, branch of photovoltaics provider headquartered in South Korea, said it finished the construction and grid connection of an 8.3 MW solar power plant in the southwestern province of Burdur. The system is the first part of a project totaling 18.3 MW. The construction of the remaining capacity is expected to start in 2016. In its largest solar project in Turkey so far, Hanwha Turkey has been responsible for module supply, engineering, procurement, construction (EPC), operations and maintenance (O&M) and it is also is a shareholder with 50% of the power plant, with partner Zen Enerji AŞ holding the remainder.

The company has closed a USD 20.15 million (EUR 18.6 million) for the complete system with Yapı ve Kredi Bankası AŞ.

The company launched works in August and reached grid connection in November. The plant is comprised of 31,878 polycrystalline solar modules of the type HSL60S and covers an area of 128,600 square metres. It is expected to produce 13.47 GWh per year, enough to power around 2,700 average households in Turkey. Thus the park will save around 2,700 kg of carbon emission in every year of its operation, according to the company’s calculations.

The company has closed a USD 20.15 million (EUR 18.6 million) for the complete system with Yapı ve Kredi Bankası AŞ, the press release said, adding that with a runtime of 12 years, it is the first such agreement in Turkey. The attractive return on investment is mainly driven by the state’s feed-in-tariff, Hanwha said.

In February, Hanwha SolarOne and Hanwha Q Cells merged, and the combined company is listed on Nasdaq.

Related Articles

Montenegro NECP public consultation sole coal plant shutdown 2041

Montenegro publishes NECP for public consultation – sole coal plant planned for shutdown in 2041

30 June 2025 - The retirement of the Pljevlja coal plant is planned for 2041, but it depends on a just transition and supply security, the draft NECP reads

hydrogen natural gas pipeline

Serbia plans hydrogen transport through gas pipelines

30 June 2025 - Gas transmission system operator Transportgas has invited bids for producing a study on hydrogen transport through the gas network

LONGi ignites Romania energy transition 54 1 MW BC

LONGi ignites Romania’s energy transition with 54.1 MW BC technology triumph

30 June 2025 - A PV plant in Romania's northwest is on schedule for a grid connection in the fourth quarter. It features LONGi Solar's BC modules.

Delyan Iliev, Managing Director of REIB

Energy storage in focus: How custom insurance solutions are fueling Southeast Europe’s green transition

27 June 2025 - Delyan Iliev, Managing Director of Renewable Energy Insurance Broker (REIB), talks about the critical role of custom-made insurance solutions in the success of BESS projects.