Burdur solar park gets online in record time

Published

December 1, 2015

Comments

comments icon

0

Share

Published:

December 1, 2015

Comments:

comments icon

0

Share

Hanwha Q Cells Turkey, branch of photovoltaics provider headquartered in South Korea, said it finished the construction and grid connection of an 8.3 MW solar power plant in the southwestern province of Burdur. The system is the first part of a project totaling 18.3 MW. The construction of the remaining capacity is expected to start in 2016. In its largest solar project in Turkey so far, Hanwha Turkey has been responsible for module supply, engineering, procurement, construction (EPC), operations and maintenance (O&M) and it is also is a shareholder with 50% of the power plant, with partner Zen Enerji AŞ holding the remainder.

The company has closed a USD 20.15 million (EUR 18.6 million) for the complete system with Yapı ve Kredi Bankası AŞ.

The company launched works in August and reached grid connection in November. The plant is comprised of 31,878 polycrystalline solar modules of the type HSL60S and covers an area of 128,600 square metres. It is expected to produce 13.47 GWh per year, enough to power around 2,700 average households in Turkey. Thus the park will save around 2,700 kg of carbon emission in every year of its operation, according to the company’s calculations.

The company has closed a USD 20.15 million (EUR 18.6 million) for the complete system with Yapı ve Kredi Bankası AŞ, the press release said, adding that with a runtime of 12 years, it is the first such agreement in Turkey. The attractive return on investment is mainly driven by the state’s feed-in-tariff, Hanwha said.

In February, Hanwha SolarOne and Hanwha Q Cells merged, and the combined company is listed on Nasdaq.

Related Articles

crna gora skupstina crne gore solarna elektrana

Parliament of Montenegro installs solar power plant

10 September 2025 - Montenegro is likely the first country in the former Yugoslavia to install solar panels on the roof of its parliament

September 15 – New Deadline for Applications for the Sustainable Energy Leader 2025 Competition

September 15 – new deadline for applications for 2025 Female Leader in Sustainable Energy

09 September 2025 - The application deadline for the 2025 Female Leader in Sustainable Energy competition has been extended until September 15

Environmentalists warn EU Bulgarian coal plants breaching pollution rules

Environmentalists warn EU that Bulgaria ignores coal plants breaching pollution rules

09 September 2025 - Greenpeace Bulgaria and Za Zemiata wrote a complaint to the European Commission as the authorities are ignoring environmental breaches at four coal plants

serbia croatia smart meters grids eds hep ods

Croatia installs one million smart meters, Serbia reaches 650,000

09 September 2025 - Digital or smart meters offer numerous advantages for consumers and distribution system operators