Green energy investors from around the world have the opportunity to boost their renewable energy portfolio with a unique biotech cluster in Serbia.  The cluster includes a fully operational biogas power plant, a second facility under construction, and its own on-site feedstock production.

Serbia Biotech Cluster operates a 1 MW biogas power plant with an annual production capacity of 8,300 kWh. The feed-in tariff of 20.7 euro cents per kWh is guaranteed for 12 years, enabling annual electricity sales of EUR 1.7 million.

The feed-in tariff is guaranteed for 12 years, both for operating and a power plant under construction

The new biogas facility under construction is 20% finished and has a feed-in tariff secured.

The feedstock material for the biogas plant is produced on-site, on 500 hectares of corn and wheat fields, shielding the project from market volatility and ensuring high-return electricity generation.

Developing the planned 10,000 m2 greenhouse would enable the investor to utilize 1.2 MW of thermal energy capacity, which is currently unused.

The potential investor can opt for acquiring the entire business as is or agree to let the operator complete and put into operation the second biogas plant and the greenhouse.

1.2 MW of currently unused thermal energy capacity could be utilized

The owner of the Serbia Biotech Cluster has been present in the Serbia and Bosnia and Herzegovina markets since 2007. The company has developed ten greenfield investments and five energy projects in the two countries.

For further details regarding the project and the investment opportunity, write to greendeals@balkangreenenergynews.com.

If you are a developing a renewable energy project in the region of Southeast Europe, if you ideally reached Ready to Build stage in project development, and are looking for an investor, or you want to sell your green energy power plant in operations, feel free to write to us. We will help you find one.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

ems ai transmission

EMS plans to use AI in construction approvals

21 November 2024 - EMS has decided to automate its construction approval procedure by introducing state-of-the-art AI solutions

IPTO ENCS cybersecurity grid

Greece’s IPTO joins European Network for Cyber Security

21 November 2024 - The European Network for Cyber Security (ENCS) has announced that IPTO has officially joined the network as a full member

montenegro gvozd epcg nordex agreement

Montenegro’s power utility EPCG begins construction of Gvozd wind farm

21 November 2024 - Wind farm Gvozd will be the first large-scale power generation facility to be built by EPCG in more than 40 years

Bulgarian waterworks firm installs in pipe hydropower generator

Bulgarian waterworks firm installs in-pipe hydropower generator

21 November 2024 - A waterworks and sewerage firm in Bulgaria produces electricity using an in-pipe hydropower device in a supply line