Croatian firm ENNA takes over 87.5 MW solar project in Romania

solar enna romania

Photo: Pexels

Published

April 28, 2025

Country

Comments

comments icon

0

Share

Published:

April 28, 2025

Country:

Comments:

comments icon

0

Share

Croatian energy company ENNA Solar, part of ENNA Group, has signed an agreement with Austria-based Kraftfeld Energy to acquire an 87.52 MW ready-to-build solar power plant project in Romania.

ENNA Solar plans to start construction in the third quarter of 2025, with the solar power plant expected to be fully operational and connected to the grid by the third quarter of 2026, according to a press release from the Croatian company.

“The investment, valued at around EUR 60 million, represents our first large-scale project outside of Croatia and one of our biggest green energy production investments to date,” said Boštjan Napast, President of the Management Board of ENNA Group.

The plant is expected to generate an average of 133 GWh a year

The solar power plant will be built in Giurgiu county, near the town of Mihăilești, 25 kilometers southwest of Bucharest. It would cover an area of 93 hectares, approximately the size of 130 football fields, ENNA stated. Its expected average annual electricity output is 133 GWh.

In the site’s close vicinity, Israel-based Nofar is building the 146 MW Ghimpați solar power plant, while the locations for its 169 MW Iepurești plant and 74 MW Slobozia facility are nearby as well.

Austria’s Kraftfeld Energy, which developed the Mihăilești project, owns and operates solar farms and energy storage systems in several European countries, primarily Romania, Hungary, Croatia, and Austria.

The investment in the solar power plant in Romania aligns with ENNA Group’s 10-year development plan, which includes investments totaling EUR 330 million in solar in Croatia and abroad, according to the press release.

ENNA also develops wind farms, geothermal projects, and battery storage systems

In addition to solar, ENNA also invests in wind farms, battery storage systems, and geothermal energy projects. It already has around 50 MW of completed renewable energy projects or projects in an advanced stage of readiness, as well as approximately 350 MW in various stages of development.

In the geothermal sector, ENNA has two active geothermal power plant projects in Croatia, with a capacity of 20 MW and 15 MW, respectively, representing a total investment of EUR 240 million.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

RatedPower webinar Power the Balkans optimizing solar and BESS with RatedPower

Webinar summary: How to design PV and BESS in the Balkans faster and smarter with RatedPower software

25 October 2025 - RatedPower has organized a webinar to present its software that makes it faster and easier to design and build PV and battery storage facilities

Negative prices to form "bathtub" curve in Greece as photovoltaics keep growing

Negative prices to form so-called bathtub curve in Greece as photovoltaics keep growing

24 October 2025 - The latest energy modeling in Greece shows ever-decreasing prices around noon, due to the expected continuation of the PV capacity surge

Romania call additional wind power auction 290 MW

Romania issues call for additional wind power auction for 290 MW

24 October 2025 - Wind farm project developers in Romania can bid by November 24 for state aid in the form of contracts for difference – CfDs

croatia-public-call-grants-bess-batteries-firms

Croatia allocates EUR 50 million for prosumers in business sector to install BESS

23 October 2025 - Battery energy storage systems offer additional benefits for companies that produce their own electricity