Romania issues call to first CfD auction for wind, solar power

Romania issues call to first CfD auction for wind, solar power

Photo: iStock

Published

September 12, 2024

Country

Comments

comments icon

0

Share

Published:

September 12, 2024

Country:

Comments:

comments icon

0

Share

Romania kickstarted a competitive process for awarding CfD contracts for wind and photovoltaic projects of 1 GW and 500 MW, respectively. The Ministry of Energy said it would complete the first such auction by January 20. The subsidy scheme is worth EUR 3 billion.

After approving the subsidy mechanism for contracts for difference (CfDs) for wind and solar power projects, Romania issued its first call. The deadline for submissions is November 18.

The European Commission greenlit the overall scheme, worth EUR 3 billion for 5 GW, half a year ago. The first auction call was planned years earlier.

Minister of Energy Sebastian Burduja noted that Romania was the first European Union member state that obtained funds for the purpose from the Modernisation Fund. “The more bidders we have, the more we will be able to accelerate the change needed to increase renewable energy production capacity at a competitive cost,” he stated.

Ministry of Energy slashes ceiling auction prices

Wind power projects have a quota of 1 GW while solar power projects can get state aid for an overall 500 MW. The ministry plans to auction the remaining onshore capacity next year. The contracts would last 15 years.

Under a CfD, the government pays the private operator the difference for the electricity that it sells if the market price is lower than the price in its contract. When it’s the other way around, the utility returns the difference.

Interestingly, ceiling prices were cut from the levels that were initially announced. Onshore wind power project developers can get a maximum of EUR 82 per MWh instead of EUR 93 per MWh. In the PV segment, the highest possible bid is EUR 78 per MWh or EUR 13 per MWh less than Burduja said in March.

Qualification phase lasts until December 9

Potential participants are required to submit a technical offer to qualify, with the necessary data including the target commission date. The other part is the financial bid in euros. Romania’s transmission system operator Transelectrica is evaluating the applications.

Companies can submit questions by September 30, ahead of a conference scheduled to take place on October 10. The tender calendar shows that applicants would be notified by December 9 whether they passed the qualification phase.

The deadline for filing appeals regarding eligibility is December 11. The financial bids will be opened on December 16, when the winners will be announced, the Ministry of Energy revealed. They would get the CfDs to sign by December 20, according to the schedule, and they are required to do so by January 20.

Of note, Romania is also introducing a competitive process for capacity allocation in the transmission grid for power plant projects.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

serbia eu region bef 2026 energy ministers panel cooperation western balkans

Western Balkan energy ministers: Alternative supply routes and regional cooperation are key to energy security

15 May 2026 - Energy ministers from Azerbaijan, Bosnia and Herzegovina, Montenegro, North Macedonia, and Serbia met at Belgrade Energy Forum 2026

Greece Papastavrou Serbia North Macedonia join Vertical Corridor gas interconnections

Greece’s Papastavrou: Serbia, North Macedonia to join Vertical Corridor with gas interconnections

15 May 2026 - Minister of Environment and Energy of Greece Stavros Papastavrou said the Vertical Corridor would be expanded to North Macedonia and Serbia

Emblematic Ag. Dimitrios lignite plant shuts down today in Greece

Ag. Dimitrios shutdown today leaves Greece with last coal plant

15 May 2026 - Today is the last day of operation of the Agios Dimitrios thermoelectric station, Greece's largest lignite-fired facility

Japan PowerX battery investments EPCG factory Montenegro

Japan-based PowerX eyes battery investments with EPCG, factory in Montenegro

14 May 2026 - PowerX from western Japan signed a deal with Montenegro's state-owned EPCG on planning 500 MWh of battery storage in the Balkan country