Renewables

North Macedonia’s DSO launches interactive map of free capacity for connecting solar power plants

north macedonia evn interactive map saltirovski solar grid connections

Photo: Elektrodistribucija

Published

August 15, 2024

Country

Comments

comments icon

1

Share

Published:

August 15, 2024

Country:

Comments:

comments icon

1

Share

North Macedonia’s distribution system operator Elektrodistribucija is probably the first in the Western Balkan region and beyond to produce an interactive map of free capacity for connecting solar power plants to the distribution grid.

The interest among households, firms and investors all over the world in installing photovoltaic plants to become prosumers or suppliers is growing every day.

Obtaining a grid connection from distribution system operators (DSOs) is a key step. It is a novelty for both sides, so there is plenty of room to accelerate and simplify the procedure.

Saltirovski: When we decided to make an interactive map, there was no such map in any country in the region and beyond

Sasho Saltirovski, managing director of Elektrodistribucija DOOEL, part of EVN Group, told Balkan Green Energy News that at the time when the firm decided to make an interactive map, there was no such tool in any country in the region and beyond.

It was an even greater motive for the team to provide information to all users of the power distribution system on how to connect to the distribution network, in the simplest and most interactive way possible.

The goal, in Saltirovski’s words, was to inform everyone interested quickly and for free. Unnecessary administrative steps such as submitting requests to the DSO require a lot of Elektrodistribucija’s time and effort, too, he explained.

Grid connections were approved for PV plants with a combined capacity of 600 MW

north macedonia evn saltirovski interactive map solar grid connections

Great interest among households, firms and investors is demonstrated by the fact that Elektrodistribucija has connected PV facilities with a total capacity of 600 MW over the last few years, out of which prosumers operate 230 MW, and producers own 370 MW. Moreover, it issued grid connection approvals for another 600 MW in photovoltaics.

According to Saltirovski, the procedure was also initiated for solar power plants of a few thousand megawatts in total.

On the other hand, the maximum electricity consumption at the distribution level in the country is about 700 MW, during summer, when the production of PV facilities is the highest, the CEO pointed out. It opens up technical issues related to the reliability of transmission and distribution systems, he added.

The main goal of the interactive map is to provide investors with signals on available locations in real time

It also means that the North Macedonian DSO’s remaining capacity for the integration of solar power plants is almost used up.

The interactive map is intended to be a snapshot of the currently available capacity in the distribution system as well the capacity for which potential producers have initiated connection procedures.

“The main purpose of the interactive map is to give potential investors the signals on locations in real time. It prevents unnecessary expenses for the purchase of land and starting the procedure of designing PV plants that won’t be able to be connected to the power distribution grid,” Saltirovski said.

Digitalization and data transparency will reduce administrative tasks in Elektrodistribucija

Digitalization and data transparency will also reduce the administrative work for the employees who communicate with potential investors, according to the DSO.

In Saltirovski words, it is another benefit for investors, because the same employees can then accelerate the installation of connections. Existing and potential investors consider it to be a very positive step, he added.

Elektrodistribucija has a team responsible for digital solutions based on GIS technology, which the map is based on. A combination of geographic functionalities and technical data produced a very satisfying final result, Saltirovski asserted.

Prosumers are connected in less than a month

north macedonia evn interactive map saltirovski solar grid

The time it takes for new electricity producers to connect to the Elektrodistribucija’s distribution network depends on several factors. If it is a prosumer, implying an existing connection and necessary technical criteria, there is only the administrative procedure. It takes no longer than 30 days, and often much less.

If it is a greenfield investment, connection time depends on the required grid upgrade. Saltirovski said power producers on the distribution grid are most often outside urban areas, at locations without energy infrastructure.

When the grid must be upgraded, connection time is between several months and several years

That’s why in most cases it is necessary to build several kilometers of medium voltage network and a substation or upgrade existing ones.

In such situations, connection time is between several months and several years, depending on how long it takes to purchase the equipment and obtain all permits, the CEO revealed.

It includes project design, paperwork and, the most complex part, solving property issues, Saltirovski stressed.

Comments (1)
Will Polen / August 22, 2024

Congratulations, Sasho!

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

DRI OMV Petrom Romania largest physical PPA

DRI, OMV Petrom sign Romania’s largest physical PPA so far

21 December 2024 - The new physical solar power purchase agreement between DRI and OMV Petrom is the largest ever in Romania

Renewable energy project frenzy in Greece defies curtailments, grid constraints

Renewable energy project frenzy in Greece defies curtailments

20 December 2024 - Applications for new renewable energy projects continued unabated in Greece in 2024 according to Independent Power Transmission Operator

north macedonia esm kfw bogdanci bitola solar wind uncev Moritz Remé

North Macedonia’s ESM secures loan, grant for solar projects, wind farm Bogdanci

20 December 2024 - The solar power plants will be installed within coal mining and energy complexes REK Bitola and REK Oslomej

Electricity sector officials visit Albania trailblazing photovoltaic plants GIZ regional decarbonization project

Electricity sector officials visit Albania’s trailblazing photovoltaic plants as part of GIZ regional decarbonization project

20 December 2024 - GIZ organized a field trip and presentations in Albania for energy ministries, electricity DSOs and regulators in the Western Balkans