Fortis Energy secures preliminary grid permits for three wind projects in Serbia

fortis energy serbia wind farms

Photo: Fortis Energy

Published

August 8, 2024

Country

,

Comments

comments icon

0

Share

Published:

August 8, 2024

Country:

,

Comments:

comments icon

0

Share

Fortis Energy has obtained preliminary grid connection permits in Serbia for three wind projects with an overall capacity of 509.5 MW.

Serbia’s transmission system operator Elektromreža Srbija (EMS) issued formal statements on electricity grid connections for wind park projects Vranje, of 171 MW, and Gornjak – 194.4 MW, Fortis Energy said.

According to the company, the preliminary license process is ongoing for its 144 MW Juhor wind project.

With a capacity of 509.4 MW in total, the wind power plants will generate 1.5 billion kWh of renewable energy, equivalent to the annual consumption of 750,000 households, and prevent the emission of 350,000 tonnes of CO2 annually.

The investments in three projects are estimated at a combined EUR 550 million

Wind measurements for the wind park sites and preliminary wind resource assessments are underway, Fortis Energy stressed.

The company estimated the investments in the three projects at a combined EUR 550 million. They support a comprehensive value chain across various sectors, including civil works, electrical engineering, logistics, maintenance, security, and telecommunications, Fortis Energy said.

Of note, a week ago Fortis Energy said that it acquired a 180 MW photovoltaic project in Serbia. It will include 36 MWh of battery capacity, the firm added.

September 1 marks the start of the new interval for the preparation of grid connection studies

On April 20, Serbia’s TSO EMS completed the first interval of preparation of studies for the connection of power plants and other facilities to the transmission grid under the new decree on electricity delivery and supply.

Bank guarantees for solar, wind and hydropower projects and substations were provided for 28 facilities with an overall capacity of 4,000 MW. Developers of 51 investments in total, divided into two groups, had to submit them by June 24 or July 1.

Three weeks ago EMS announced that September 1 would mark the start of the new study preparation interval. The deadline to submit applications is August 1.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

north macedonia forum skopje declaration sustainable energy undep sanja bozinovska grigorian liguti

Skopje Declaration signed as International Forum on Energy for Sustainable Development wraps up

31 October 2025 - The three-day International Forum on Energy for Sustainable Development (IFESD-14) brought together over 500 participants from 70 countries

serbia seepex eps intraday idc market contract

EPS to help SEEPEX strengthen Serbia’s intraday power market

31 October 2025 - SEEPEX believes this collaboration will position its IDC market as a trusted and dynamic platform for trading across the region and beyond

PPC building three battery storage facilities in Greece

PPC building three battery storage facilities in Greece

30 October 2025 - PPC Group has launched the construction of a battery energy storage system in the area of its Amyntaio coal plant

eds restructuring tender

Serbia’s distribution system operator plans comprehensive restructuring

30 October 2025 - EDS has launched a tender to select a consultant to develop a restructuring plan and support its implementation