Fortis Energy secures preliminary grid permits for three wind projects in Serbia

fortis energy serbia wind farms

Photo: Fortis Energy

Published

August 8, 2024

Country

,

Comments

comments icon

0

Share

Published:

August 8, 2024

Country:

,

Comments:

comments icon

0

Share

Fortis Energy has obtained preliminary grid connection permits in Serbia for three wind projects with an overall capacity of 509.5 MW.

Serbia’s transmission system operator Elektromreža Srbija (EMS) issued formal statements on electricity grid connections for wind park projects Vranje, of 171 MW, and Gornjak – 194.4 MW, Fortis Energy said.

According to the company, the preliminary license process is ongoing for its 144 MW Juhor wind project.

With a capacity of 509.4 MW in total, the wind power plants will generate 1.5 billion kWh of renewable energy, equivalent to the annual consumption of 750,000 households, and prevent the emission of 350,000 tonnes of CO2 annually.

The investments in three projects are estimated at a combined EUR 550 million

Wind measurements for the wind park sites and preliminary wind resource assessments are underway, Fortis Energy stressed.

The company estimated the investments in the three projects at a combined EUR 550 million. They support a comprehensive value chain across various sectors, including civil works, electrical engineering, logistics, maintenance, security, and telecommunications, Fortis Energy said.

Of note, a week ago Fortis Energy said that it acquired a 180 MW photovoltaic project in Serbia. It will include 36 MWh of battery capacity, the firm added.

September 1 marks the start of the new interval for the preparation of grid connection studies

On April 20, Serbia’s TSO EMS completed the first interval of preparation of studies for the connection of power plants and other facilities to the transmission grid under the new decree on electricity delivery and supply.

Bank guarantees for solar, wind and hydropower projects and substations were provided for 28 facilities with an overall capacity of 4,000 MW. Developers of 51 investments in total, divided into two groups, had to submit them by June 24 or July 1.

Three weeks ago EMS announced that September 1 would mark the start of the new study preparation interval. The deadline to submit applications is August 1.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Emblematic Ag. Dimitrios lignite plant shuts down today in Greece

Ag. Dimitrios shutdown today leaves Greece with last coal plant

15 May 2026 - Today is the last day of operation of the Agios Dimitrios thermoelectric station, Greece's largest lignite-fired facility

Japan PowerX battery investments EPCG factory Montenegro

Japan-based PowerX eyes battery investments with EPCG, factory in Montenegro

14 May 2026 - PowerX from western Japan signed a deal with Montenegro's state-owned EPCG on planning 500 MWh of battery storage in the Balkan country

EVN Macedonia BESS 10 MW into operation at solar park

EVN Macedonia puts BESS of 10 MW into operation at its solar park

13 May 2026 - EVN Macedonia commissioned a battery energy storage system within its Probištip photovoltaic plant in North Macedonia

Energy companies confront dual mandate keeping supply secure while accelerating green transition BEF 2026

Energy companies in Western Balkans confront dual mandate – keeping supply secure while accelerating green transition

13 May 2026 - Companies in the region have challenges in energy security, decarbonization and digitalization, and the key is investing in production, the grid and batteries, according to the panel on power system transition at Belgrade Energy Forum 2026