BW ESS, Penso Power, Shell create pioneering battery storage partnership

BW ESS, Penso Power Shell battery storage tolling

Photo: BW ESS

Published

August 7, 2024

Country

Comments

comments icon

0

Share

Published:

August 7, 2024

Country:

Comments:

comments icon

0

Share

Energy storage owner and operator BW ESS and its partner, Penso Power, have signed a seven-year agreement with Shell Energy Europe Limited for the proposed 100 MW / 330 MWh Bramley battery energy storage system (BESS).

The deal between BW ESS, Penso Power, and Shell represents a new model for agreements in the development and operation of energy storage.

It is the first announced long-term tolling agreement for a single BESS asset in Great Britain, creating a template for a new revenue structure that will help to unlock energy storage market opportunities across Europe, BW ESS said.

The Bramley Battery Energy Storage System is currently under construction in Hampshire in the United Kingdom.

The fixed-price tolling agreement provides revenue certainty for BW ESS and Penso Power while Shell will trade the Bramley BESS into a range of ancillary services and wholesale markets, the announcement reads.

Bramley is expected to be the longest duration BESS in the UK at the time of commissioning,

According to Recharge, so far energy storage projects have been implemented with profit-sharing or floor agreements. The former envisages splitting profit from a battery between the owner and the operator. With the latter model, the operator guarantees a level of revenue for a battery asset. Above that level, profits are split through a profit-sharing agreement. Below it, the operator pays the difference to the owner.

BW ESS said the 100 MW / 330 MWh Bramley site is the first project in Europe to deploy Sungrow’s PowerTitan 2.0 liquid cooled BESS – a system that combines a 2.5 MW power conversion system using integrated string inverters and a 5 MWh battery into a single container.

It has enabled BW ESS and Penso Power to deliver a 330 MWh project with a relatively small project footprint. Bramley is expected to be the longest-duration BESS in the UK at the time of commissioning, which is expected in Q4 this year, the company added.

Strømsø: The tolling agreement helps enable the market’s shift away from short-term frequency response towards load shifting

CEO of BW ESS Erik Strømsø said that Bramley showcases his company’s commitment to advancing energy storage solutions that set the bar for the wider market – while pioneering new models for project financing and operation.

“This tolling agreement, which has been some time in the making, demonstrates the attractiveness of longer-duration, higher-performance battery systems. It not only secures long-term revenues for Bramley, but also helps enable the market’s shift away from short-term frequency response towards load shifting,” Strømsø explained.

Tanna: Tolls have been a feature of conventional energy trading for many years

According to Richard Thwaites, CEO of Penso Power, the floor contract that the firms agreed with Shell on their Minety battery storage project back in 2020 became a template for the industry, and the new tolling agreement for Bramley breaks new ground. It represents a coming of age for the battery energy storage sector, he added.

Rupen Tanna, Head of Power and Systematic Trading at Shell Energy Europe, noted that tolls have been a feature of conventional energy trading for many years. By extending the business model to battery storage, Shell has the trading experience to add significant value, while supporting the UK’s energy transition, he stressed.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Bulgarian firm install pilot hydropower plant pontoon Danube

Bulgarian firm to install pilot hydropower plant on pontoon on Danube

16 July 2025 - Looking to build several hydroelectric plants on pontoons on the Danube in Bulgaria, a local company intends to install a 20 kW pilot facility in Vidin

north macedonia stip wind farm alcaraz calderon mickoski

Construction of largest wind farm in Western Balkans kicks off in Štip in North Macedonia

16 July 2025 - The Štip wind farm will cover an area of 326 hectares in the municipalities of Karbinci, Radoviš, and Štip

bih solar republic of srpska rogatica Elektrohertz concession

Elektrohertz gets concession for solar project in Republic of Srpska

16 July 2025 - Republic of Srpska, one of the two entities constituting Bosnia and Herzegovina, is set to host another solar power plant

Bulgarian battery factory Exeron X-BESS gets EU strategic status

Bulgarian battery factory Exeron X-BESS gets EU strategic status

16 July 2025 - IPS is opening the Exeron X-BESS factory as one of only six strategic projects in the EU designated under the Net Zero Industry Act