Romania simplifies, speeds up permitting for renewable energy projects

Romania simplifies, speeds up permitting for renewable energy projects

Photo: Laurențiu Mihai Badea from Pixabay

Published

July 4, 2023

Country

Comments

comments icon

0

Share

Published:

July 4, 2023

Country:

Comments:

comments icon

0

Share

Romania has passed a new law to simplify and speed up the permitting process for renewable energy projects.

The changes are related to the construction of solar, wind, biomass, bioliquid, biogas, and storage facilities, substations, and other similar investments.

Law 166/2023 amends Urbanism Law 350/2001 and Construction Law 50/1991. It entered into force on June 10.

According to local media, building permits for renewable energy projects can be obtained without a zoning plan (PUZ).

A PUZ is no longer required for projects in urban areas (intra muros) and outside urban areas (extra muros). In January PUZ was abolished for extra muros land, and now also for intra muros land.

Obtaining a PUZ was one of the most time-consuming parts of the permitting process for renewable energy projects.

Renewable energy projects on extra muros plots of more than 50 hectares are prohibited

According to Wolf Theiss, Law 166/2023 must be read together with Land Law 18/1991, which addresses the exception to the restriction to build renewable energy projects on extra muros land (i.e. agricultural lands, pastures, vineyards, orchards, as well as land benefiting from improvements) that has soil fertility classes III, IV and V, provided that the projects fit within a maximum surface area of 50 hectares.

In practice, developers and investors in the industry are facing the current interpretation at the level of the Ministry of Agriculture whereby the construction of renewable energy projects on extra muros land surface areas of more than 50 hectares is forbidden, even if the investor/developer has carried out the zoning procedure of changing the land from extra muros into intra muros, the law firm said.

Law 166/23 also allows investors to obtain multiple building permits under a single urban planning certificate. It is not rare that they are developing multiple projects on a larger area of land with each of the projects spanning less than 50 hectares.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

LONGi enters energy storage market redefining industry standards with Ultimate Safety

LONGi enters energy storage market, redefining industry standards with Ultimate Safety

26 November 2025 - LONGi announced its entry into the storage sector with the launch of the LONGi Energy Storage One-Stop Solution

Enery to start building Europe's largest solar power plant in Romania

Enery to start building Europe’s largest solar power plant in Romania

25 November 2025 - Enery is preparing to break ground on a solar park of 750 MW in Romania – it would currently be Europe's largest

greece Mesochora hydropower ppc relocation study ministry

PPC receives funds for stalled Mesochora hydropower project 

25 November 2025 - Public Power Corporation has received funds to speed up its Mesochora hydropower project, stalled for 24 years

croatia social climate policy plan EU ets 2 marija vuckovic

Croatia drafts EUR 1.68 billion Social Climate Plan

25 November 2025 - The funds would be obtained from the auctions of emission allowances in the European Union and Croatia under the EU ETS 2