Renewables permits in Greece nearing 100 GW but grid lacks capacity

photovoltaics

Photo: PublicDomainPictures on Pixabay

Published

March 14, 2023

Country

Comments

comments icon

0

Share

Published:

March 14, 2023

Country:

Comments:

comments icon

0

Share

An overwhelming number of renewable energy projects in Greece have producer certificates but connection issues remain, especially for photovoltaics.

Public relations chief of the Regulatory Authority for Energy (RAE) Dionysis Papachristou recently said projects with 98.3 GW in total capacity have received at least some of the licenses. There is 25.3 GW with approved environmental terms, while another 65.1 GW is in the earlier development stages. Licenses for energy storage have reached 24.4 GW, for 356 projects.

The electric power system includes 9.8 GW of renewables in operation while final connection terms have been issued for another 10.7 GW. According to the country’s revised National Energy and Climate Plan, total renewable energy capacity needs to reach 25 GW by 2030.

However, grid issues keep causing delays. According to solar association POSPIEF’s General Secretary Petros Tsikouras, there is 1 GW in installed and licensed photovoltaic systems waiting to be connected.

POSPIEF: It often takes up to 12 months to process grid connection requests

Speaking to PV-Magazine, he added it often takes up to 12 months to process grid connection requests. The Hellenic Electricity Distribution Network Operator (HEDNO) is failing to meet deadlines, so POSPIEF is calling for investors to be allowed to build their own grid connection lines. However, the government confirmed HEDNO’s monopoly in 2020.

Government blamed for delays, accused of foul play

It should be noted that many investors who await connections have loans to pay back, suffering financial damages as a result of the delays.

Given the high interest in building renewable energy facilities, some are accusing the government of taking advantage of limited grid space by favoring companies of its own choosing. Furthermore, there have been examples of badly planned auctions, like for photovoltaic units of up to 400 kW in Crete and the Peloponnese. In both cases, some investors were found to be using special software to flood the system and have their offer accepted, so others have appealed to the courts.

Opposition parties such as Syriza and Pasok have accused the government of favoring specific interests with a recent bill on renewables and providing various exemptions a few months before the national elections.

HEDNO and IPTO to expand grid to accommodate more green energy

HEDNO and Independent Power Transmission Operator (IPTO), the transmission system operator, are upgrading the network and building lines.

IPTO, also known for its Greek acronym Admie, expects to finish the 400 kV Western Corridor for the Peloponesse by the end of April after some delay. HEDNO, or Deddie, has added plans for several substations to its ten-year development plan.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Turkish geothermal power plant operator drill for geothermal lithium

Turkish renewables firm to drill for geothermal lithium

26 July 2025 - Margün Energy intends to search for lithium in geothermal water in western Turkey, where it took over a 12 MW geothermal power plant

serbia wind farm plandiste nis met dubravka djedovic

Government of Serbia interested in taking over Plandište wind project

25 July 2025 - Plandište is one of the projects that obtained feed-in tariffs under the first quota of 500 MW for wind power plants in Serbia

Over 20,000 prosumer projects connected in Greece during last 18 months

Over 20,000 prosumer units connected in Greece in last 18 months

24 July 2025 - Households and businesses remain highly interested in becoming prosumers in Greece, although the new net billing program faces delays.

Project 81 MW solar park on coal mine in Montenegro

Project underway for 81 MW solar park on coal mine in Montenegro

24 July 2025 - The Government of Montenegro gave a provisional green light for a solar power plant of 81.1 MW in peak capacity on coal land in Pljevlja