Serbia to put coal plant Kostolac B3 into operation as early as October 2023

Dedovic Djedovic Serbia coal plant Kostolac B3 October

Foto: Dubravka Đedović / Facebook

Published

November 28, 2022

Country

Comments

0

Share

Published:

November 28, 2022

Country:

Comments:

0

Share

The last batch of equipment for the construction of the new unit of the Kostolac B thermal power plant has arrived at the site, by ship. B3 will be connected to the network in June and put into operation as early as October, Minister of Mining and Energy Dubravka Đedović said.

The construction of the biggest facility for the production of electricity in the Western Balkans in the last four decades is in its final phase. There are currently one thousand workers at the site of the future B3 unit of the Kostolac coal-fired power plant complex in Serbia, and two hundred more will be added to finish the project before the deadline, Minister of Mining and Energy Dubravka Đedović said. She visited the location with Ambassador of China Chen Bo.

“The new facility will run at all the highest environmental protection standards and it will be the cleanest of all the units that we have,” Đedović claimed and added that the plan is to connect Kostolac B3 to the network on June 28 – St. Vitus Day according to the Julian calendar. The unit will be in operation as early as October, she pointed out.

The minister noted that Serbia needs to covver 10% of its electricity needs from imports in winter time. More than 60 domestic companies are involved in the construction, she asserted.

There are one thousand workers at the site of the future B3 unit of the Kostolac coal-fired power plant complex in Serbia, and two hundred more will be added to finish the project before the deadline

“Special gratitude goes to the miners of the Drmno open pit mine, which will have its capacity grown by 30% with this project. Thank you to all the miners in all our open pit mines that are working hard for us to have sufficient quantities of coal and import the least electricity possible,” she added.

Ambassador Chen Bo pointed out that many more challenges lay ahead in the implementation of the project, but also expressed confidence that the contractor, China Machinery Engineering Corp. (CMEC), would put maximum efforts to finish the thermal power plant in time.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

drina-hydropower-plants

Court annuls environmental permit for Drina hydropower project

02 May 2024 - The construction of large hydropower plants on the Drina is facing new delays, after a court ruling to scrap the environmental permit for HPP Foča

el-dorado-electricity-imports-north-macedonia-rke

North Macedonia: ‘Solar El Dorado’ cuts electricity imports to 2.75%

02 May 2024 - In 2023, North Macedonia's new solar capacity increased by as much as 251% compared to 2022

EU-completing-Green-Deal-Industrial-Plan-Net-Zero-Industry-Act

EU completing Green Deal Industrial Plan as Net Zero Industry Act awaits go-ahead

01 May 2024 - The European Union's Net Zero Industry Act is about to come into force, completing legislative work within the Green Deal Industrial Plan

Dubravka Dedovic Djedovic Handanovic reappointed Serbia minister of energy mining

Dubravka Đedović Handanović reappointed as Serbia’s minister of energy, mining

30 April 2024 - Minister of Energy and Mining Dubravka Đedović Handanović is keeping her seat in the new cabinet while Minister of Environmental Protection Irena Vujović is also becoming deputy prime minister