Renewables

Croatia rejects green electricity projects of 2.5 GW in total

Photo: Michelle Raponi from Pixabay

Published

October 28, 2022

Country

Comments

comments icon

0

Share

Published:

October 28, 2022

Country:

Comments:

comments icon

0

Share

Croatia has finally begun to clear the mess from excessive number of applications for the construction of renewable power plants. The Ministry of Economy and Sustainable Development published a list of projects that did not receive energy approval.

The Ministry of Economy and Sustainable Development has announced that it has rejected 33 applications for energy approval for power plants with a total capacity of 2.5 gigawatts (GW).

The ministry’s move comes at a time when investors are largely dissatisfied over long permitting procedures. They submitted 216 applications until February, but the ministry only issued the first energy approval two weeks ago.

Solar projects with a planned overall capacity of 1.5 GW have been rejected

The requests were rejected in line with article 133 of the Law on the Electricity Market, the ministry said.

The group of rejected projected requests consists of 26 solar power plants, five wind farms, one hydropower plant and one cogeneration plant. The ministry said it didn’t accept applications for photovoltaic facilities with a combined capacity of 1,510 MW, wind power plants with 684 MW in total, 150 MW in hydropower projects and 85 MW in cogeneration.

Of note, according to the new Law on the Electricity Market, investors are required to submit applications by January 19. Energy approvals are a necessary step in the development of green energy projects.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Finalists of the 2026 European Sustainable Energy Awards announced

Finalists of the 2026 European Sustainable Energy Awards announced

05 May 2026 - Public voting for the best European clean energy projects and leaders is now open, within European Sustainable Energy Awards 2026

renalfa ipp bess oslomej solar power plant

Renalfa IPP starts installing 200 MWh battery system at solar plant in North Macedonia

05 May 2026 - The co-located BESS is being installed at Oslomej, a solar power plant with a peak capacity of 65.8 MW at a former coal mine, Renalfa said

world energy crisis war renewables boom Simon Stiell un

Energy crisis fueled by Iran war makes economic logic of renewables impossible to ignore

04 May 2026 - The energy crisis fueled by the Iran war has made the economic logic of renewables impossible to ignore, according to Simon Stiell

Batteries enable Bulgaria import cheap electricity domestic production exceeds demand

Batteries enable Bulgaria to import cheap electricity even when domestic production exceeds demand

04 May 2026 - Bulgaria's abundant energy storage enables importing electricity at low, zero or negative prices even when domestic production exceeds demand