Study for Kostolac wind park to be done by October

Published

July 6, 2016

Country

Comments

comments icon

0

Share

Published:

July 6, 2016

Country:

Comments:

comments icon

0

Share

Predrag Đorđević, manager for key investment projects at Electric Power Company of Serbia (EPS), said the feasibility study for the planned wind park in Kostolac would be finished by October.

In an interview for the June issue of Energija, the state-owned utility’s magazine, he added the development of the main design will ensue, followed by the preparation of tender documents for the procurement of equipment and works. So far the location and places for wind turbines were chosen and research was conducted, while the process lasted several years, he said.

As Đorđević pointed out, EPS accepted the principles of preventive planning in order to avoid negative impact on the environment, in this case in order to protect birds and bats. The study was conducted according to the standards of the European Union, he said.

The wind farm will be located 90 kilometers east of capital Belgrade. Sites Drmno, Petka, Ćirikovac and Klenovik are abandoned mining facilities and slag and ash ponds at the Kostolac coal basin. Total potential size of the facility is 50 square kilometers, while the particular locations vary from 1.5 to 10 square kilometers, according to the article in Energija.

Đorđević said the results of the preliminary feasibility study showed that in this area it is possible to build a wind farm with 20 turbines and a total installed capacity of 50 to 60 MW. The service life of the wind farm is projected at 20 to 25 years, and terrain features indicate a very favourable choice of location, he added.

A solar power plant of 9.9 MW is also planned to be installed in the area of the coal complex.

Related Articles

Negative prices to form "bathtub" curve in Greece as photovoltaics keep growing

Negative prices to form so-called bathtub curve in Greece as photovoltaics keep growing

24 October 2025 - The latest energy modeling in Greece shows ever-decreasing prices around noon, due to the expected continuation of the PV capacity surge

Romania call additional wind power auction 290 MW

Romania issues call for additional wind power auction for 290 MW

24 October 2025 - Wind farm project developers in Romania can bid by November 24 for state aid in the form of contracts for difference – CfDs

croatia-public-call-grants-bess-batteries-firms

Croatia allocates EUR 50 million for prosumers in business sector to install BESS

23 October 2025 - Battery energy storage systems offer additional benefits for companies that produce their own electricity

romania repono bess purchase Argeș

Repono acquires BESS project for 404 MWh in Romania

23 October 2025 - The Argeș project reached a ready-to-build stage. It has a contract with Transelectrica for a grid connection