The ongoing ecological reconstruction of Montenegro’s thermal power plant (TPP) Pljevlja will not require a temporary shutdown during 2023, but a 7-month stoppage in the plant’s operation is planned for 2024, according to Zoran Šljukić, who manages the overhaul project.

Šljukić confirmed for Vijesti that the ecological reconstruction will be completed by October 15, 2024, to be followed by a 5-month trial operation period.

Šljukić: TPP Pljevlja’s ecological reconstruction will be completed by October 15, 2024

The reconstruction of TPP Pljevlja, which is expected to bring the coal-fired power plant’s nitrogen, sulfur and particulate matter emissions into line with EU regulations, and extend its lifespan, was launched in April this year.

Šljukić noted that CO2 emissions are not covered by the ecological reconstruction as they are taxed in Montenegro, at EUR 24 per ton, with revenues going towards environmental projects.

The plant, operated by state power utility Elektroprivreda Crne Gore (EPCG), must meet EU standards in order to continue to operate, as was agreed with the Energy Community Secretariat under the opt-out regime. TPP Pljevlja, with a capacity of 225 MW, accounts for 40% of Montenegro’s domestic electricity production.

The installation of equipment is expected to begin in March 2023

Building works are going as planned, and a third has already been completed. All of the building works are expected to be finished by the end of October this year, and the installation of equipment is planned to begin in March 2023, according to Šljukić.

The equipment from China is due to arrive in Montenegro in December, according to the article. The reconstruction of TPP Pljevlja is being carried out by a consortium led by China’s Dongfang Electric International Corp.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Serbia drafts just transition action plan public debate

Serbia drafts just transition action plan

30 May 2025 - The Ministry of Mining and Energy has published a draft just transition action plan and launched a public debate

Regional Power Sector Exchange Western Balkans disitribution system operator dso grids ohrid giz

Third Regional Power Sector Exchange in Ohrid: Power grids at core of energy transition

30 May 2025 - The third Regional Power Sector Exchange of the Western Balkans gathered over 80 energy professionals from the Western Balkans

two solar power plants egesa enerji vojvodina

Turkish Egesa Enerji to build two solar power plants in Serbia’s Vojvodina province

30 May 2025 - Turkish company Egesa Enerji has launched a project to build two solar power plants in Vojvodina, with a total nominal capacity of 8.6 MW

Green for Growth Fund partnership Swedish International Development Cooperation Agency Sida

Green for Growth Fund launches partnership with Swedish International Development Cooperation Agency

30 May 2025 - GGF and the Swedish International Development Cooperation Agency are expanding green lending in the Western Balkans and the EU's Eastern Neighborhood