Renewables

Romanian firm Nord Wind Power to install 130 MW wind farm in Iași

Romanian Nord Wind Power 130 MW wind farm Iasi

Photo: Mylene2401 from Pixabay

Published

February 14, 2022

Country

Comments

0

Share

Published:

February 14, 2022

Country:

Comments:

0

Share

A company that counts a Romanian senator among its shareholders obtained the technical approval for its planned 129.5 MW wind power plant in the country’s east. It is scheduled to be completed in 2025, but Nord Wind Power indicated it may sell the project or team up with a larger player.

Transmission system operator Transelectrica gave a green light last month for Nord Wind Power’s first technical grid connection request for its wind farm project in Dumești in Iași county, breaking the ice for this year’s large renewable energy investments, Ziarul Financiar reported. The document shows the endeavor is envisaged to be finished in 2025.

The 129.5 MW project in Romania’s east is worth EUR 100 million. The article adds one of the shareholders of Nord Wind Power, with 16.3%, is Chair of the Senate Committee for Agriculture, Food Industry and Rural Development George Scarlat. His company Fermsuin also holds a stake.

Scarlat: The government doesn’t support domestic firms in the sector

Scarlat was also the secretary of state at the Ministry of Agriculture and Rural Development. Corina Lorenţ is registered as the majority shareholder. The company was founded almost a decade ago, but it reported no turnover for four years now.

Nord Wind Power may not implement the project, or at least not by itself, according to Scarlat’s statement quoted by the news outlet. He revealed there are issues with financing and said the government gives no support whatsoever to domestic firms in the strategic sector.

It means such projects can be carried out by large companies with easy access to financial instruments, Scarlat added, hinting at the possibility of a sale.

However, both domestic and foreign companies have pledged billions of euros for a range of mid-sized and giant renewable energy and hydrogen projects in Romania.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

CMS legal experts energy storage Belgrade Energy Forum

CMS legal experts on energy storage to take part in Belgrade Energy Forum

29 April 2024 - Experts on energy storage projects and regulations from law firm CMS Reich-Rohrwig Hainz will take part in Belgrade Energy Forum 2024

Renewable electricity share Turkey 50

Renewable electricity share in Turkey nears 50%

29 April 2024 - Renewable sources had a 49.3% share in Turkey last month. Minister Mehmet Şimşek said USD 100 billion would be invested within ten years.

Lightsource-bp-solar-park-modules

UK-based Lightsource bp to build Europe’s second-biggest solar park in Greece

29 April 2024 - British solar energy developer Lightsource bp is launching works on a 560 MW photovoltaic park in Greece, in a EUR 395 million investment

Belgrade-Energy-Forum-platform-major-renewable-energy-deals-join-it

Belgrade Energy Forum is the platform for major renewable energy deals – join it!

29 April 2024 - The Belgrade Energy Forum event platform is facilitating major partnerships, financing agreements and contracting opportunities in Southeast Europe