KOSTT signs connection agreement for 192 MW for solar park in Kosovo*

KOSTT 192 MW solar park Kosovo

Photo: KOSTT

Published

March 11, 2021

Country

Comments

comments icon

0

Share

Published:

March 11, 2021

Country:

Comments:

comments icon

0

Share

Kosovo’s power transmission system operator inked its third big deal in three months for the connection of planned renewable power plants to the grid. Dukagjini Solar intends to install two photovoltaic units of 96 MW of alternating current power each. The planned combined peak capacity is 250 MW.

The Transmission, System and Market Operator (KOSTT) of Kosovo* said its Chief Executive Officer Mustafë Hasani signed an agreement for a solar park in Peja-Peć that is expected to start production in 2023. The deal is for a capacity of 192 MW in alternating current (AC) terms, while the peak level, expressed in direct current, will be 250 MW, project managers said.

Dukagjini Solar, a joint venture between Ibex Energy and Jaha Solar, is developing the project near the western border. It consists of units Terstenik and Sverke, with an AC capacity of 96 MW each. Ibex Energy’s Chairman Christopher James and Jaha Solar’s Chairman Fadil Hoxha represented the company at the signing ceremony. Jaha Solar is a domestic manufacturer of solar power panels.

Alternating current capacity, expressed in MWac or kWac, is the maximum that can enter the grid and it depends on the total size of inverters. The peak capacity of a photovoltaic facility is in direct current and the units are MWp or kWp.

The solar park will be connected to the 110 kV transmission network through a new line and connected to the 400/110 kV Peja 3 substation, according to KOSTT.

Last month it signed an equivalent agreement for Solar Energy Group’s future 150 MWp photovoltaic system in Gjakova, also known as Đakovica. It follows a deal from December with Air Energy 2 for two wind farms and a solar power plant with a combined 99.6 MW in Kamenica, but the details weren’t specified.

Data from the Energy Regulatory Office show Kosovo* had only 10 MW installed in on-grid solar power plants in 2019.

* This designation is without prejudice to positions on status and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

montenegro gvozd epcg nordex Ibrahim Özarslan

Montenegro’s power utility EPCG begins construction of Gvozd wind farm

21 November 2024 - Wind farm Gvozd will be the first large-scale power generation facility to be built by EPCG in more than 40 years

Bulgarian waterworks firm installs in pipe hydropower generator

Bulgarian waterworks firm installs in-pipe hydropower generator

21 November 2024 - A waterworks and sewerage firm in Bulgaria produces electricity using an in-pipe hydropower device in a supply line

serbia solar djedovic zivkovic petka kostolac

Serbia’s solar capacity at 166 MW and rising

20 November 2024 - The solar capacity has increased by almost 24 MW in three months, according to data from the Ministry of Mining and Energy

montenegro france afd loan spajic vukovic

Montenegro signs EUR 50 million loan agreement with France’s AFD

20 November 2024 - AFD will support Montenegro's reforms in waste management, renewable energy, sustainable forestry, and climate action