Podveležje wind farm starts producing electricity

Podvelezje wind farm starts producing electricity

Photo: EPBiH

Published

January 18, 2021

Comments

comments icon

0

Share

Published:

January 18, 2021

Comments:

comments icon

0

Share

Wind turbines at locations 7 and 8 of the Podveležje wind farm have been given a test run, generating the first amount of electricity that was injected into the transmission network.

The tests on the first two wind turbines, out of a total of 15 installed within the 48 MW Podveležje wind farm, marked the beginning of the final phase of the functional testing of the wind turbines and the start of electricity production.

State-owned power utility ElektroprivredaBosne i Hercegovine (EPBiH) began construction on its first wind farm in May last year.

According to the EPBiH, the contractor, a consortium led by Siemens, will successively examine the functionality of the remaining units over the coming period.

The Supervision and Management System (SCADA) for Podveležje wind farm has been installed and partially tested, enabling full remote monitoring and operation from the EPBiH’sdispatch center for production management, located in Sarajevo, EPBiH said on its website (video).

The estimated output of the wind farm is 130 GWh annually. EPBiHalso plans to build a 30 MW solar power plant near the Podveležje wind farm.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

geothermal well croatia

Croatia confirms major geothermal resource for district heating

30 June 2025 - The tested geothermal well could meet nearly 60% of district heating needs in Velika Gorica, the Croatian Hydrocarbon Agency says.

Montenegro NECP public consultation sole coal plant shutdown 2041

Montenegro publishes NECP for public consultation – sole coal plant planned for shutdown in 2041

30 June 2025 - The retirement of the Pljevlja coal plant is planned for 2041, but it depends on a just transition and supply security, the draft NECP reads

hydrogen natural gas pipeline

Serbia plans hydrogen transport through gas pipelines

30 June 2025 - Gas transmission system operator Transportgas has invited bids for producing a study on hydrogen transport through the gas network

LONGi ignites Romania energy transition 54 1 MW BC

LONGi ignites Romania’s energy transition with 54.1 MW BC technology triumph

30 June 2025 - A PV plant in Romania's northwest is on schedule for a grid connection in the fourth quarter. It features LONGi Solar's BC modules.