Podveležje wind farm starts producing electricity

Podvelezje wind farm starts producing electricity

Photo: EPBiH

Published

January 18, 2021

Comments

comments icon

0

Share

Published:

January 18, 2021

Comments:

comments icon

0

Share

Wind turbines at locations 7 and 8 of the Podveležje wind farm have been given a test run, generating the first amount of electricity that was injected into the transmission network.

The tests on the first two wind turbines, out of a total of 15 installed within the 48 MW Podveležje wind farm, marked the beginning of the final phase of the functional testing of the wind turbines and the start of electricity production.

State-owned power utility ElektroprivredaBosne i Hercegovine (EPBiH) began construction on its first wind farm in May last year.

According to the EPBiH, the contractor, a consortium led by Siemens, will successively examine the functionality of the remaining units over the coming period.

The Supervision and Management System (SCADA) for Podveležje wind farm has been installed and partially tested, enabling full remote monitoring and operation from the EPBiH’sdispatch center for production management, located in Sarajevo, EPBiH said on its website (video).

The estimated output of the wind farm is 130 GWh annually. EPBiHalso plans to build a 30 MW solar power plant near the Podveležje wind farm.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

serbia electricity market rules ems nikola tosic balancing

Serbia’s new electricity market rules bring important changes

12 February 2026 - Nikola Tošić, Market Division Manager at Serbia's transmission system operator EMS, explains new electricity market rules

YESS Power integrates battery system with Novaci PV plant in North Macedonia

YESS Power integrates battery system with Novaci PV plant in North Macedonia

12 February 2026 - Turkey-based YESS Power has commissioned, as a contractor, the first grid-scale BESS in North Macedonia and the region

romania ppc bess battery salbatica wind farm

PPC to install 60 MWh battery system at Sălbatica wind farm

11 February 2026 - PPC operates the Sălbatica 1 and Sălbatica 2 wind farms, with a combined capacity of 140 MW, located in Tulcea County

wind farm bijela alcazar

Montenegro clears environmental impact study for 118.8 MW Bijela wind farm

11 February 2026 - The Environmental Protection Agency has approved the environmental impact assessment for the 118.8 MW Bijela wind farm