Update: Site for Tuzla 7 coal project ready as Energy Community hints at sanctions

Construction site for Tuzla 7 coal project Energy Community sanctions

Photo: Construction site for the unit 7 in Tuzla coal power plant (EPBiH)

Published

October 28, 2020

Comments

comments icon

0

Share

Published:

October 28, 2020

Comments:

comments icon

0

Share

While power utility Elektroprivreda BiH (EPBiH) is handing over the construction site of the new unit 7 in Tuzla coal power plant to Chinese partners, the Secretariat of the Energy Community is announcing possible sanctions over state aid.

EPBiH has initiated the construction of a 450 MW unit to replace obsolete units 3, 4 and 5 at thermal power plant Tuzla. It earlier secured a EUR 614 loan from the Export-Import Bank of China or Chexim – China Exim Bank, and China’s Gezhouba consortium was hired to build it.

As part of the dispute settlement procedure, a hearing will be held before the advisory board on December 9

According to daily newspaper Dnevni Avaz, BiH is in danger of sanctions from the Energy Community. The possibility was confirmed by Barbora Poyner, Communication Officer in the Secretariat of the Energy Community.

The secretariat claims that the Tuzla 7 project received illegal state aid, so in March last year it initiated a dispute settlement procedure against BiH.

BiH may be left without certain rights which derive from the Energy Community Treaty

Poyner earlier announced that as part of this procedure, a hearing will be held on November 6 before the Advisory Board of the Energy Community, to which BiH representatives have been invited. The hearing is one of the steps in resolving disputes initiated by the secretariat. Today, the Energy Community has issued an update and said the event is postponed for December 9.

If it is proven that BiH has breached the state aid acquis regarding the Tuzla 7 project, the country’s rights deriving from the Energy Community Treaty could be limited.

For example, it could impact the right to vote or the country will be excluded from meetings or mechanisms envisaged by the treaty, she added.

EPBiH prepared EUR 200,000 for lawyers

A few weeks ago, EPBiH announced a tender for the procurement of legal services in the dispute settlement procedure with the secretariat. The estimated value of the procurement is EUR 200,000 while the deadline to submit bids is November 2.

Construction site ready for China’s Gezhouba consortium

In the meantime, a consortium of Zenica-based ITC, Integral Inženjering Banja Luka and Prijedor Putevi, selected by EPBiH, is completing preparatory works for the construction of unit 7.

The value of the activities that started in November 2019 is almost EUR 9.5 million.

Senad Salkić, executive director for capital investments at EPBiH, said the construction site is almost completely ready and that it would be handed over to Chinese partners in the next few days.

Experts from EPBiH and the partners from China are jointly preparing the basic design of the project

Experts from EPBiH are developing the basic design of the project with representatives of the partners from China. According to Salkić, the Chinese side will then prepare the main project and start obtaining building permits.

The preparatory works included cleaning the area between 320,000 and 340,000 square meters, filling about 380,000 cubic meters of material, installing five kilometers of underground pipelines, extending the main collector by almost 800 meters and installing a fence of 1,800 meters around the construction site.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Serbia drafts just transition action plan public debate

Serbia drafts just transition action plan

30 May 2025 - The Ministry of Mining and Energy has published a draft just transition action plan and launched a public debate

Regional Power Sector Exchange Western Balkans disitribution system operator dso grids ohrid giz

Third Regional Power Sector Exchange in Ohrid: Power grids at core of energy transition

30 May 2025 - The third Regional Power Sector Exchange of the Western Balkans gathered over 80 energy professionals from the Western Balkans

two solar power plants egesa enerji vojvodina

Turkish Egesa Enerji to build two solar power plants in Serbia’s Vojvodina province

30 May 2025 - Turkish company Egesa Enerji has launched a project to build two solar power plants in Vojvodina, with a total nominal capacity of 8.6 MW

Green for Growth Fund partnership Swedish International Development Cooperation Agency Sida

Green for Growth Fund launches partnership with Swedish International Development Cooperation Agency

30 May 2025 - GGF and the Swedish International Development Cooperation Agency are expanding green lending in the Western Balkans and the EU's Eastern Neighborhood