Norwegian company laid first part of transmission cable

Published

March 23, 2015

Country

Comments

0

Share

Published:

March 23, 2015

Country:

Comments:

0

Share

The first, 140 kilometer phase of installing the Tivat‒Pescara underwater line, which shall be 390 kilometers long, was completed in mid-March by Nexans, web portal Analitika said.

The Norwegian company is Italy’s Terna’s partner and it is yet to set another 250 km cable, which shall be connected to the first one. Another cable, 500 meters away from the first one, will be installed by the Italian company Prysmian, and the works may start in a year.

The 1 GW Italy-Montenegro underwater transmission cable project  has faced numerous delays because of Croatian government’s decision to explore the potential for oil and gas basins located under its territorial waters.

Montenegro will be profiting EUR 10-40 million per year, as 20 percent of transmission earnings belongs to Montenegrin company CGES. Terna’s share shall be 80 percent for a period of 40 years.

The contract was signed on November 23, 2010 between the Government of Montenegro, Montenegrin company CGES and Italian company Terna. KfW Development Bank and European Bank for Reconstruction and Development (EBRD) provided majority of project’s financing.

 

Tags: ,

Related Articles

europe flexibility seasonal balancing iea report

Flexibility needs to be met by demand response, batteries, hydrogen, but also thermal, hydropower plants – IEA

03 May 2024 - The report Managing the Seasonal Variability of Electricity Demand and Supply analyzes the situation in Europe, India, and Indonesia

drina-hydropower-plants

Court annuls environmental permit for Drina hydropower project

02 May 2024 - The construction of large hydropower plants on the Drina is facing new delays, after a court ruling to scrap the environmental permit for HPP Foča

el-dorado-electricity-imports-north-macedonia-rke

North Macedonia: ‘Solar El Dorado’ cuts electricity imports to 2.75%

02 May 2024 - In 2023, North Macedonia's new solar capacity increased by as much as 251% compared to 2022

EU-completing-Green-Deal-Industrial-Plan-Net-Zero-Industry-Act

EU completing Green Deal Industrial Plan as Net Zero Industry Act awaits go-ahead

01 May 2024 - The European Union's Net Zero Industry Act is about to come into force, completing legislative work within the Green Deal Industrial Plan