Norwegian company laid first part of transmission cable

Published

March 23, 2015

Country

Comments

comments icon

0

Share

Published:

March 23, 2015

Country:

Comments:

comments icon

0

Share

The first, 140 kilometer phase of installing the Tivat‒Pescara underwater line, which shall be 390 kilometers long, was completed in mid-March by Nexans, web portal Analitika said.

The Norwegian company is Italy’s Terna’s partner and it is yet to set another 250 km cable, which shall be connected to the first one. Another cable, 500 meters away from the first one, will be installed by the Italian company Prysmian, and the works may start in a year.

The 1 GW Italy-Montenegro underwater transmission cable project  has faced numerous delays because of Croatian government’s decision to explore the potential for oil and gas basins located under its territorial waters.

Montenegro will be profiting EUR 10-40 million per year, as 20 percent of transmission earnings belongs to Montenegrin company CGES. Terna’s share shall be 80 percent for a period of 40 years.

The contract was signed on November 23, 2010 between the Government of Montenegro, Montenegrin company CGES and Italian company Terna. KfW Development Bank and European Bank for Reconstruction and Development (EBRD) provided majority of project’s financing.

 

Tags: ,

Related Articles

Record battery installations EU 2025 Bulgaria enters top 3

Record battery installations in EU in 2025 as Bulgaria enters top 3

28 January 2026 - The European Union added 27.1 GWh of battery capacity last year, marking a 12th consecutive record – driven by utility-scale storage

croatia ante susnjar minister renewables subsidies jutarnji list energy conference

Šušnjar: Croatia allocated EUR 4 billion so far to boost renewables; subsidies for wind, solar to end

28 January 2026 - Minister of Economy Ante Šušnjar said at an energy conference that the money could have been put to better use

končar power transformer tanks Siemens factory

Croatia’s Končar to invest EUR 500 million in manufacturing over three years

27 January 2026 - Končar has opened a power transformer tank factory with Siemens Energy and it plans to develop anti-drone protection for energy facilities

Research project in Romania explores the use of agrisolar systems with batteries in agriculture

Researchers in Romania developing agrisolar system with batteries

27 January 2026 - An agrisolar power plant with batteries is being set up in a research and demonstration project in Romania