The Government of Croatia has adopted a decree on quotas to incentivize the production of electricity from renewable energy sources and high-efficiency cogeneration, which marks the introduction of premiums for stimulus.

The decree has been adopted on the basis of the energy sector development strategy until 2030, with projections until 2050, and the national energy and climate plan (NECP) for the period 2021 to 2030.

Two programs of state incentives were prepared based on defined quotas

The quotas determined by the decree represent the total amount of installed capacity of the facilities for which market premium contracts and power purchase agreements with a guaranteed purchase price can be signed, the decree reads and the Renewable Energy Sources of Croatia (RES Croatia) reported.

Based on the quotas, two programs of state incentives were prepared. One is in line with the GBER procedure (General Block Exemption Regulation) and it will be approved by the Ministry of Finance for auctions held every year.

HROTE conducts auctions for the award of market premiums and for the conclusion of PPAs with a guaranteed purchase price

The second program will be sent for approval to the European Commission. It covers the period 2020-2022 and refers to the approval of the auctions for the market premiums.

The programs will be submitted by the Croatian Energy Market Operator (HROTE), given that it is in charge of granting incentives.

HROTE has the right and obligation to determine the timeline for using quotas

HROTE has the right and obligation to determine the timeline for using quotas, minding that depending on the technology, some contracts can be implemented in a shorter or longer period. The maximum must not exceed four years from the signing of the contract for premiums.

HROTE also conducts auctions for the allocation of market premiums and for the signing of the power purchase agreements (PPAs) with a guaranteed purchase price. Annual quotas for individual technologies should ensure market competition and the planned start of power production in new facilities.

Earlier, Maja Pokrovac, Managing Director at RES Croatia, said projects worth EUR 1.6 billion are prepared and that they would be implemented after the introduction of premiums.

Total quota 2,265,000 kW (2.265 GW)

The groups of production facilities:

  • Solar power plants from 50 kW up to 500 kW – 210,000 kW
  • Solar power plants from 500 kW up to 10 MW – 240,000 kW
  • Solar power plants with more than 10 MW – 625,000 kW
  • Hydropower plants up to 50 kW – 4,000 kW
  • Hydropower plants from 50 kW up to 500 kW – 10,000 kW
  • Hydropower plants from 500 kW up to 10 MW – 10,000 kW
  • Wind farms with more than 3 MW – 1,050,000 kW
  • Biomass power plants from 50 kW up to 500 kW – 6,000 kW
  • Biomass power plants from 500 kW up to 2 MW – 20,000 kW
  • Biomass power plants from 2 MW up to 5 MW – 15,000 kW
  • Geothermal power plants with more than 500 kW – 20,000 kW
  • Biogas power plants from 50 kW up to 500 kW – 15,000 kW
  • Biogas power plants from 500 kW up to 2 MW – 30,000 kW
  • Innovative technologies with support from the EU – 10,000 kW.
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

CJR Renewables 102 MW Urleasca wind farm Romania

CJR Renewables completes construction of 102 MW Urleasca wind farm in Romania

09 October 2025 - The Urleasca wind farm in Brăila county in eastern Romania is complete, contractor CJR Renewables said

world dnv energy transition energy transition outlook 2025

Policy changes in US will have marginal impact on global energy transition

09 October 2025 - AI energy use may seem alarming, but it is projected to stay below EV charging and the cooling of buildings, DNV calculated

turkey teias world bank loan Humberto Lopez Orhan Kaldirim Alparslan Bayraktar

Turkey’s TEİAŞ signs USD 750 million loan contract with World Bank

08 October 2025 - A USD 750 million loan will be used for the Transforming Power Transmission System Project, Turkey’s transmission system operator TEİAŞ said

Romania Hidroelectrica hydropower battery storage

Romania’s Hidroelectrica to equip hydropower plants with battery storage

08 October 2025 - Romanian state-owned power utility Hidroelectrica plans to integrate battery storage with all its run-of-river hydropower plants