Burdur solar park gets online in record time

Published

December 1, 2015

Comments

comments icon

0

Share

Published:

December 1, 2015

Comments:

comments icon

0

Share

Hanwha Q Cells Turkey, branch of photovoltaics provider headquartered in South Korea, said it finished the construction and grid connection of an 8.3 MW solar power plant in the southwestern province of Burdur. The system is the first part of a project totaling 18.3 MW. The construction of the remaining capacity is expected to start in 2016. In its largest solar project in Turkey so far, Hanwha Turkey has been responsible for module supply, engineering, procurement, construction (EPC), operations and maintenance (O&M) and it is also is a shareholder with 50% of the power plant, with partner Zen Enerji AŞ holding the remainder.

The company has closed a USD 20.15 million (EUR 18.6 million) for the complete system with Yapı ve Kredi Bankası AŞ.

The company launched works in August and reached grid connection in November. The plant is comprised of 31,878 polycrystalline solar modules of the type HSL60S and covers an area of 128,600 square metres. It is expected to produce 13.47 GWh per year, enough to power around 2,700 average households in Turkey. Thus the park will save around 2,700 kg of carbon emission in every year of its operation, according to the company’s calculations.

The company has closed a USD 20.15 million (EUR 18.6 million) for the complete system with Yapı ve Kredi Bankası AŞ, the press release said, adding that with a runtime of 12 years, it is the first such agreement in Turkey. The attractive return on investment is mainly driven by the state’s feed-in-tariff, Hanwha said.

In February, Hanwha SolarOne and Hanwha Q Cells merged, and the combined company is listed on Nasdaq.

Related Articles

North Macedonia draft law envisages renewable energy auctions for CfDs

North Macedonia’s draft law envisages renewable energy auctions for CfDs

14 August 2025 - North Macedonia's draft Law on the Use of Energy from Renewable Sources covers auctions, CfDs, prosumers and renewable energy communities

serbia russia nuclear energy Alexander Botsan-Kharchenko dubravka djedovic

Đedović Handanović discusses Serbia’s nuclear power plan with Russian ambassador

14 August 2025 - Minister of Mining and Energy Dubravka Đedović Handanović met with the Ambassador of the Russian Federation Alexander Botsan-Kharchenko

Floating solar farm ready to be merged with North Sea offshore wind park

Floating solar farm ready to be merged with North Sea offshore wind park

14 August 2025 - Oceans of Energy has assembled its floating PV plant Nymphaea Aurora in three days, to integrate it into a giant offshore wind park

Romania completes second round renewable energy auctions third wind quota unallocated

Romania completes second round of renewable energy auctions – third of wind quota unallocated

13 August 2025 - Romania completed its second round of renewable energy auctions. More than one third of the wind power quota wasn't allocated and prices rose.