News

HPP Zvornik enters EUR 70 million overhaul

Published

October 12, 2015

Comments

0

Share

Published:

October 12, 2015

Comments:

0

Share

One of the oldest hydropower plants (HPPs) on the Drina river is being refurbished in a project worth EUR 70 million. The 96 MW Zvornik facility of four units has a dam holding a 25 kilometre long artificial lake, and the four-year project will extend its working life by 40 years, according to Electric Power Industry of Serbia, the government-controlled utility.

Minister of energy and mining Aleksandar Antić said the works are financed from a loan from the German development bank KfW. He stressed the HPPs capacity would be increased by 30% and that the production would shoot up 15% or 70 million KWh a year, translating into three to five million euros per year.

Voith Hydro will take 12 months for the refurbishment of each of the units. Antić said domestic companies are hired for works equivalent to EUR 17 million. KfW had already financed the overhaul of the nearby HPP Bajina Bašta, said Arne Gooss, the bank’s head for Serbia.

Related Articles

europe flexibility seasonal balancing iea report

Flexibility needs to be met by demand response, batteries, hydrogen, but also thermal, hydropower plants – IEA

03 May 2024 - The report Managing the Seasonal Variability of Electricity Demand and Supply analyzes the situation in Europe, India, and Indonesia

Artificial intelligence can detect the toxicity of chemicals

Artificial intelligence can detect toxicity of chemicals

03 May 2024 - Swedish scientists have developed a method using artificial intelligence (AI) to identify toxic chemicals based solely on knowledge of their molecular structure

IPTO suspends all electricity imports until May 7 to protect the Greek system

Greece suspends electricity imports until May 7 to protect system

03 May 2024 - The Greek Independent Power Transmission Operator (IPTO) has announced the suspension of all electricity imports during the hours around noon

drina-hydropower-plants

Court annuls environmental permit for Drina hydropower project

02 May 2024 - The construction of large hydropower plants on the Drina is facing new delays, after a court ruling to scrap the environmental permit for HPP Foča