Eol prvi seeks extension for Trusina wind project deadline

Photo: Pixabay

Published

October 5, 2015

Comments

comments icon

0

Share

Published:

October 5, 2015

Comments:

comments icon

0

Share

The holder of a 30-year concession for the construction of Trusina, a 51 MW wind park in the Republic of Srpska, worth BAM 150 million (EUR 76.6 million), has asked for an extension of the deadline for the project’s completion, according to news daily Nezavisne novine.

Concession holder Eol prvi doo from Nevesinje is late in performing the construction works for a wind park at Trusina mountain near the town in Bosnia and Herzegovina’s southeast. The project is funded by Kermas Ltd., headed by Darko Končar and based in Britain, according to the schedule set out in the agreement with the government.

Local media earlier reported that the construction of the Trusina wind park should have been completed last year. However, 2018 is now considered as the most probable completion date for the technical works, the entity’s energy authorities say. The other autonomous part of BiH is called the Federation of Bosnia and Herzegovina.

According to Zlatko Mandžuka, who heads Eol prvi, the company is late in signing a grid connection contract with Transco (Elektroprenos-Elektroprijenos BiH ad Banja Luka), the national transmission utility. He blamed the delay on the damage from the past war and the disagreements between that company and Elektroprivreda RS, Srpska’s power utility, on how to add the power plant. The director noted the entity’s government gave the goahead for Kermas to become the owner of 87% of the concession and finance the project with the help of a bank.

Once completed, the wind farm is expected to produce 160 GWh per year, enough to power 40,000 households.

Related Articles

Greece had record renewable production and curtailments in 2025

Greece achieves record renewables output but also curtailments in 2025

05 February 2026 - Renewable energy production reached a new high last year in Greece, amidst increased curtailments and a low lignite share

wind turbine eu china goldwind

Chinese wind turbine supplier Goldwind probed in EU over alleged foreign subsidies

05 February 2026 - The European Commission launched a preliminary investigation in 2024 into several companies active in the EU wind sector, including Goldwind

Saudi Arabia to build 2 GW of solar power in Turkey within 5 GW deal

Saudi Arabia to build 2 GW of solar power in Turkey within 5 GW deal

04 February 2026 - Saudi Arabia signed an agreement for its companies to build solar power plants totaling 2 GW in two provinces in Turkey

North Macedonia unveils EUR 5 7 billion plan power plants energy storage

North Macedonia unveils EUR 5.7 billion plan for new power plants, energy storage

02 February 2026 - North Macedonia's 2026 plan includes 67 power plant projects of at least 1 MW each, for investments totaling an estimated EUR 3.74 billion