Reservoir Capital Corp. reported positive development in construction permitting for its Brodarevo hydroelectric projects. The company said it has been engaged in the updating of documentation in recent months to comply with changes to Serbia’s planning and construction laws introduced earlier in the year. In recent weeks, Reservoir secured positive opinions regarding the issue of building permits from a number of key state-controlled institutions.

There was a positive opinion on the project for the construction of the first phase for hydropower plant Brodarevo 2, by the State Audit Committee, and a positive technical review by the Faculty of Civil Engineering in Belgrade, which holds the state license. There was a decision by the Institute for Nature Conservation of Serbia to allow the construction of two road tunnels and the relocation of the main M21 highway.

Reservoir is a renewable energy company engaged in the development of a 59.1 MW hydroelectric project at Brodarevo on the River Lim, and the Vranjska Banja geothermal project, both in southern Serbia, the press release said.

The company said  it secured several positive opinions from relevant authorities for the projects on Lim river in May.

Related Articles

Prosumers in Romania neck and neck commercial PV plants capacity

Prosumers in Romania are neck and neck with commercial PV plants in capacity

20 August 2025 - Prosumers in Romania don't have a much larger total capacity anymore than commercial solar power plants, a segment accelerating in expansion

Winners of the 2025 Just Transition Young Voices Awards announced 

Winners of 2025 Just Transition Young Voices Awards revealed

20 August 2025 - Tringë Shkodra, Ani Gogokhia, and Kateryna Pereloma have been announced as the winners of the 2025 Just Transition Young Voices Awards

Econergy connects 87 MW Oradea solar PV project in Romania to the grid

Econergy’s 87 MW Oradea solar park in Romania starts commercial operation

19 August 2025 - Econergy Renewable Energy has connected its 87 MW Oradea solar power plant to Romania’s national electricity grid