Podveležje wind farm project presented in Mostar by EP BiH

Photo: EP BiH

Published

March 14, 2018

Comments

comments icon

0

Share

Published:

March 14, 2018

Comments:

comments icon

0

Share

The Elektroprivreda BiH (EP BiH) power company organized a presentation of its project to build the Podveležje windfarm in Mostar. The new power production facility will be built using a loan from the German development bank KfW and EP BiH funds.

Representatives of the German company Fichtner helped EP BIH to present the project.

The total value of the project is estimated to stand at around 162 million Convertible Marks (EUR 81 million) with the KfW bank approving a loan of EUR 65 million and a grant of EUR 400,000 by the time of the presentation and the EP BiH securing the remaining EUR 17,864,600 to complete the project.

EP BiH officials told the presentation that the project is part of the power company’s development policy which will help with the economic development of the Mostar area. They said the project will be split into three stages, the first of which is underway, and added that the plan is to start producing electric energy in the Podveležje windfarm by mid-2019.

The EP BiH plan for the first stage is to draw up construction plans, procure 15 turbines of up to 3 MW and build the foundations and accompanying infrastructure for the wind farm. The second stage will see the construction of 30 110 kV substations and lay a high voltage cable along with a grounding network while the third stage will see the construction of local roads and platforms, the presentation was told.

The construction and reconstruction of local roads for the needs of the windfarm will be done by the consortium formed by HP Investing Mostar, Amitea Mostar and Izgradnja Tojaga Mostar. The ABB Zagreb company will set up the 30 110 kV substations and lay the high voltage cable system.

EP BiH officials could not specify the name of the company that will install the turbines because the tender for that stage is underway.

The EP BiH said on its website that the Ministry of Energy, Mining and Industry of the BiH Federation issued an energy permit on May 24, 2016, to the JP Elektroprivreda Bosne i Hercegovine – Sarajevo company for the construction of the Podveležje windfarm for an installed power of up to 48 MW, with a planned annual production of 115-119 GWh within the Mostar city area at the Podveležje site at Mali Grad and Sveta Gora.

The power permit was issued for the May 24, 2016 – May 24, 2019 period.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

slovenia subsidies prosumers solar batteries borzen

New EUR 30 million in subsidies for Slovenian prosumers

03 March 2026 - The funds are intended for legal entities, and the subsidy scheme will be implemented by electricity market operator Borzen

eu entsog report biomethane renewable gas injections

ENTSOG: Renewable gas injections in EU grids increase 12%

03 March 2026 - The European Network of Transmission System Operators for Gas has published its report on annual renewable gas injections into gas networks

solar output snow winter

Record solar output in Romania pushes power prices into negative territory

02 March 2026 - On Friday at 11:39 a.m., commercial solar output, excluding prosumers, reached 2,048 MW, while demand stood at slightly over 6,000 MW

Power imports dropped almost at zero for Greece in January

Power imports in Greece drop to nearly zero in January

02 March 2026 - Greece saw the balance of electricity exchanges with neighboring markets change rapidly during the last couple of years. It became a net exporter.