Serbia and Romania power interconnector near completion

Photo: Pixabay

Published

October 31, 2017

Comments

comments icon

0

Share

Published:

October 31, 2017

Comments:

comments icon

0

Share

The Resita-Pančevo transmission line construction between Romania and Serbia is getting closer to the end. The role of the interconnection between two countries is of strengthening national electricity systems as well as the South-East European one.

Romania’s national electricity transmission company, Transelectrica announced that it completed the crossing of the border to Serbia with the 400 kV Resita (Romania) – Pancevo (Serbia) transmission line. This is one of the final stages in the realization of the interconnection project on the Romania-Serbia relationship, according to energynomics.

The 400 kV Resita-Pancevo is a project of common interest at European level. It will allow also the elimination of major congestions in the Romanian and Serbian power systems as well as the increase of the transfer capacity between two countries and across the South-Eastern Europe.

“I am glad we have been able to unlock this important project for Transelectrica, in recent months. The works at the Resita-Pancevo line have a high level of complexity and engage specialists from many fields. In the West [of Romania], there is a major project – Mid Continental East Corridor – which contributes crucially to the strategic priorities of the European Union for trans-European energy infrastructure. The Resita – Pancevo line is part of this project, but also of ours, and of the Government’s strategy of closing the 400 kV ring”, said Corina Popescu, CEO of Transelectrica, according to The Diplomat.

Construction of the Serbian section of the overhead power line towards Reșița in Romania started at Pančevo substation northeast of capital Belgrade, in early 2016. The project worth EUR 24.7 million was planned to be completed by the end of this year for the trial run, the transmission system operator Elektromreža Srbije (EMS) announced back then.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

serbia eu region bef 2026 energy ministers panel cooperation western balkans

Western Balkan energy ministers: Alternative supply routes, regional cooperation are key to energy security

15 May 2026 - Energy ministers from Azerbaijan, Bosnia and Herzegovina, Montenegro, North Macedonia, and Serbia met at Belgrade Energy Forum 2026

Greece Papastavrou Serbia North Macedonia join Vertical Corridor gas interconnections

Greece’s Papastavrou: Serbia, North Macedonia to join Vertical Corridor with gas interconnections

15 May 2026 - Minister of Environment and Energy of Greece Stavros Papastavrou said the Vertical Corridor would be expanded to North Macedonia and Serbia

Emblematic Ag. Dimitrios lignite plant shuts down today in Greece

Ag. Dimitrios shutdown today leaves Greece with last coal plant

15 May 2026 - Today is the last day of operation of the Agios Dimitrios thermoelectric station, Greece's largest lignite-fired facility

Japan PowerX battery investments EPCG factory Montenegro

Japan-based PowerX eyes battery investments with EPCG, factory in Montenegro

14 May 2026 - PowerX from western Japan signed a deal with Montenegro's state-owned EPCG on planning 500 MWh of battery storage in the Balkan country