Serbia and Romania power interconnector near completion

Photo: Pixabay

Published

October 31, 2017

Comments

comments icon

0

Share

Published:

October 31, 2017

Comments:

comments icon

0

Share

The Resita-Pančevo transmission line construction between Romania and Serbia is getting closer to the end. The role of the interconnection between two countries is of strengthening national electricity systems as well as the South-East European one.

Romania’s national electricity transmission company, Transelectrica announced that it completed the crossing of the border to Serbia with the 400 kV Resita (Romania) – Pancevo (Serbia) transmission line. This is one of the final stages in the realization of the interconnection project on the Romania-Serbia relationship, according to energynomics.

The 400 kV Resita-Pancevo is a project of common interest at European level. It will allow also the elimination of major congestions in the Romanian and Serbian power systems as well as the increase of the transfer capacity between two countries and across the South-Eastern Europe.

“I am glad we have been able to unlock this important project for Transelectrica, in recent months. The works at the Resita-Pancevo line have a high level of complexity and engage specialists from many fields. In the West [of Romania], there is a major project – Mid Continental East Corridor – which contributes crucially to the strategic priorities of the European Union for trans-European energy infrastructure. The Resita – Pancevo line is part of this project, but also of ours, and of the Government’s strategy of closing the 400 kV ring”, said Corina Popescu, CEO of Transelectrica, according to The Diplomat.

Construction of the Serbian section of the overhead power line towards Reșița in Romania started at Pančevo substation northeast of capital Belgrade, in early 2016. The project worth EUR 24.7 million was planned to be completed by the end of this year for the trial run, the transmission system operator Elektromreža Srbije (EMS) announced back then.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Most read articles on Balkan Green Energy News in 2025

Most read articles on Balkan Green Energy News in 2025

02 January 2026 - Battery storage and digitalization stepped into the spotlight in 2025, according to the readers of Balkan Green Energy News, which marked its tenth anniversary with the best results so far

serbia eps solar 1 gw Dubravka djedovic handanovic dusan zivkovic

Đedović Handanović: Construction of 1 GW solar project to start in 2026

31 December 2025 - The shareholders' assembly of of Elektroprivreda Srbije adopted the Three-Year Business Plan for the period 2026-2028

China commissions world largest open sea PV plant

China completes grid connection of world’s largest open sea PV plant

31 December 2025 - CHN Energy fully connected to the mainland grid a 1 GW solar power system that it built on the open sea off the coast of Shandong in China

Electrica call contractors for large PV parks in Romania

Electrica issues call for contractors for large PV parks in Romania

31 December 2025 - Electrica, in which the Romanian Government holds almost 50%, is again seeking contractors for its solar projects Satu Mare 3 and Bihor 1