Serbia and Romania power interconnector near completion

Photo: Pixabay

Published

October 31, 2017

Comments

comments icon

0

Share

Published:

October 31, 2017

Comments:

comments icon

0

Share

The Resita-Pančevo transmission line construction between Romania and Serbia is getting closer to the end. The role of the interconnection between two countries is of strengthening national electricity systems as well as the South-East European one.

Romania’s national electricity transmission company, Transelectrica announced that it completed the crossing of the border to Serbia with the 400 kV Resita (Romania) – Pancevo (Serbia) transmission line. This is one of the final stages in the realization of the interconnection project on the Romania-Serbia relationship, according to energynomics.

The 400 kV Resita-Pancevo is a project of common interest at European level. It will allow also the elimination of major congestions in the Romanian and Serbian power systems as well as the increase of the transfer capacity between two countries and across the South-Eastern Europe.

“I am glad we have been able to unlock this important project for Transelectrica, in recent months. The works at the Resita-Pancevo line have a high level of complexity and engage specialists from many fields. In the West [of Romania], there is a major project – Mid Continental East Corridor – which contributes crucially to the strategic priorities of the European Union for trans-European energy infrastructure. The Resita – Pancevo line is part of this project, but also of ours, and of the Government’s strategy of closing the 400 kV ring”, said Corina Popescu, CEO of Transelectrica, according to The Diplomat.

Construction of the Serbian section of the overhead power line towards Reșița in Romania started at Pančevo substation northeast of capital Belgrade, in early 2016. The project worth EUR 24.7 million was planned to be completed by the end of this year for the trial run, the transmission system operator Elektromreža Srbije (EMS) announced back then.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Ember Warming 2024 global power demand rise with fossil fuels

Ember: Warming’s 2024 share of global power demand rise was covered with fossil fuels

09 April 2025 - Renewables and nuclear energy met 79,1% of 2024 global power demand growth. The fossil fuels share was bigger than the part attributed to the annual rise in temperatures.

delta green scheme flexibility households grid balancing

Delta Green launches platform in CEE for households to provide grid balancing

09 April 2025 - Delta Green claims it is the first in Central and Eastern Europe and among the first in Europe to implement such a solution

RWE PPC partnership starting build 567 MW PV capacity

RWE-PPC partnership starting to build 567 MW of PV capacity

08 April 2025 - The Meton Energy joint venture of PPC and RWE has taken the final investment decision for two photovoltaic projects north of Thessaloniki

bih hydropower plants epbih vranduk janjici court EIA

Court annuls environmental permits for EPBiH’s hydro projects Janjići, Vranduk

07 April 2025 - Hydropower projects Janjići and Vranduk are being developed by state-owned power company Elektroprivreda BiH