5 MW cogeneration facility in Slatina by GGE to be completed in 2018 

Photo: GGE

Published

November 29, 2017

Country

Comments

comments icon

0

Share

Published:

November 29, 2017

Country:

Comments:

comments icon

0

Share

The implementation of GGE’s largest energy efficiency project – the construction of a cogeneration of heat and power (CHP) plant in Croatian Slatina municipality is expected to be completed by summer of 2018, the regional energy services company GGE said in a statement.

The total investment is worth EUR 24 million and construction works have begun in September.

Consisting of a steam boiler running on wood chips, with a steam turbine and generator for electrical power, the plant will produce both electric and heat energy. It will have a 5 MW capacity and annually produce 40 GWh of electric energy, which is enough to power 500 households.

The Croatian energy market operator (HROTE) has signed a 14-year contract for the purchase of the electricity produced.

„Investing in a biomass-powered CHP plant is a natural step for our company, given that we are a leader in the ESCO business in South Eastern Europe, as well as a company that is completely oriented towards renewable sources of energy, energy savings and investments in clean energy projects. The Slatina CHP project will implement best available technology equipment with the highest level of energy efficiency and lowest greenhouse gas emissions,“ Siniša Janjušević, head engineer on the project and GGE Project Leader said.

Preparations for the development of the Slatina CHP project took six months, given that we were highly focused on choosing the right concept for the plant, with the best suited, most efficient and effective technology.

“Negotiations with the equipment supplier, who is also the contractor building the entire project, took another few months, which is further proof of how committed all the participants are to achieving excellence. Team work has been and will remain very important throughout all the phases of the project, and we will continue to build good cooperation between partners, focusing our attention on the precision and accuracy of the performance of the plant,” said Marko Podlesek, Director of GGE’s Heat & Power Division, responsible for the entire project.

This commercial technology for the simultaneous production of heat and power will be one of the largest projects of its kind in the region and represents a benchmark for GGE as well as the Slatina municipality.

The newly built cogeneration plant will employ 15 people from the municipality once it begins operations.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Romania completes second round renewable energy auctions third wind quota unallocated

Romania completes second round of renewable energy auctions – third of wind quota unallocated

13 August 2025 - Romania completed its second round of renewable energy auctions. More than one third of the wind power quota wasn't allocated and prices rose.

DRI secures financing for Vacaresti solar park in Romania

13 August 2025 - DRI obtained non-recourse loans of up to EUR 60 million to finance its Vacaresti solar park in Romania

bih coal mines epbih sanel buljubasic

Worrying results of coal, overburden production in BiH’s power utility

13 August 2025 - Increasing coal production is the only way to stabilize the energy system in the Federation of BiH, EPBiH CEO Sanel Buljubašić said

slovenia hess hpp brezice solar power plant febr-d koncar

Slovenia’s HESS inks 9.2 MW deal for two solar power plants near HPP Brežice

13 August 2025 - Hydropower plant operator Hidroelektrarne na Spodnji Savi will install two PV plants near its Brežice hydropower plant