Serbian energy minister calls for untangling Drina hydropower deal with Italy

Photo: Ministry of energy and mining

Published

November 13, 2017

Country

Comments

comments icon

0

Share

Published:

November 13, 2017

Country:

Comments:

comments icon

0

Share

It is time to untangle the situation regarding cooperation with Italians and to start building hydropower plants on the Drina river, independently or with another partner, Serbian Minister of Mining and Energy Aleksandar Antić said after the first meeting of the Joint Energy Committee between Serbia and Republika Srpska.

In September 2011, Italy’s Seci Energia, Serbian public power utility Elektroprivreda Srbije (EPS) and Republika Srpska’s public power enterprise Elektroprivreda Republike Srpske (ERS) signed a preliminary agreement on the construction of three hydropower plants (HPP) on the Drina river.

The planned capacity was 450 MW, expected annual production 1,200 MWh and the estimated value of the investment EUR 800 million. The energy produced by the three HPPs was to be transferred to Italy. The works were supposed to start in 2013.

On Friday Serbian Energy and Mining Minister Aleksandar Antić and his Republika Srpska counterpart Petar Đokić attended the first meeting of the Joint Energy Committee in Belgrade. They announced stronger cooperation, implementation of joint energy projects and construction of the HPPs on the Drina river.

“We have had an agreement with Italians, but they have delayed it for many years. The time has finally come to untangle this situation and to build HPPs, independently or with another partner. Republika Srpska has the excellent Upper Drina project, one of the best in this part of Europe. We are interested in becoming partners in it. The Lower Drina project is also very good,” Antić said.

Energy utility directors from Serbia and RS are members of the Joint Energy Committee.

“We spent too much time hugging and kissing because we are all Serbs. I think the time has come to realize joint projects and that must be a priority,” Antić added.

Minister Petar Đokić said that four hydropower plants could be built as part of the Upper Drina project, four along the middle section of the river and three under the Lower Drina project.

Đokić recalled that Republika Srpska will build HPP Buk Bijela in cooperation with Chinese partners and that Republika Srpska would like to include Serbia in this project.

 

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

How to choose a BESS integrator for utility-scale solar projects

31 March 2026 - Solar developers need to consider four main factors when selecting the integrator for a battery energy storage system (BESS)

NGEN Group Austria Europe largest energy storage

NGEN Group breaks ground in Austria for one of Europe’s largest energy storage facilities

31 March 2026 - NGEN Austria has launched works on a two-hour BESS of 85 MW in Wagenham, set to become the biggest in the country and one of the biggest in Europe

croatia ancala biomass karlovac plant

Ancala acquires three biomass plants in Croatia

31 March 2026 - Independent infrastructure manager Ancala has acquired three biomass plants from Sherif Group in Croatia

north macedonia substaion central evn bozinovska

EVN Macedonia commissions Skopje’s first substation in 40 years

30 March 2026 - It is the first energy infrastructure of its kind built in Skopje and even in the broader region, EVN said