Electricity

Republic of Srpska doesn’t have EUR 357 million to maintain production in coal power plants

republic of srpska gacko ugljevik coal power

TPP Gacko (photo: Gacko mine and thermal power plant)

Published

December 24, 2024

Comments

comments icon

0

Share

Published:

December 24, 2024

Comments:

comments icon

0

Share

Investments required for the stable operation of the Gacko and Ugljevik mines and coal power plants are estimated at BAM 700 million (EUR 357 million). But there is no money, according to Petar Đokić, Minister of Energy and Mining of the Republic of Srpska, one of the two entities that constitute Bosnia and Herzegovina.

Minister Petar Đokić held a meeting with the boards of directors and supervisory boards of RiTE Gacko and RiTE Ugljevik, firms operating two thermal power plants with accompanying coal mines. They acknowledged the situation is difficult.

Đokić stressed the significance of sustainability of the electricity system of the Republic of Srpska. He added that securing stable production in the facilities during the winter is also important.

The meeting was attended by the CEO of state-owned power utility Elektroprivreda Republike Srpske (ERS) Luka Petrović. It is the holding company of RiTE Gacko and RiTE Ugljevik.

Coal quality is a major issue for TPP Gacko

“We cannot provide funding that would be sufficient for them to operate normally. At one point today it was said the investment needs for the sustainability of mining output and the operation of thermal power plants amount to about BAM 350 million per power plant. We would currently need to secure that much money for one, and then the other, for them to be able to take full responsibility for secure operations. We don’t have that money,” Đokić stated, BN TV reported.

ERS CEO Luka Petrović said additional funds need to be found to stabilize the operations of the coal mines and two power plants and maintain low electricity prices.

The two thermal power plants are essential for the company as they account for about 70% of its electricity production. The severity of the dire state that they are in was evident in a recent outage of about ten days in TPP Ugljevik.

According to Maksim Skoko, acting director of RiTE Gacko, the firm’s troubles are centered on the mine as investments have been insufficient for years.

Two years ago, the Polje C mine was shut down due to a landslide and now there is only low-quality coal, he pointed out.

It is why much larger quantities of fuel oil are used in the Gacko power plant, increasing expenses, Skoko added.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Battery storage investors Romania rapidly expanding project pipeline

Battery storage investors in Romania rapidly expanding project pipeline

16 August 2025 - In an rising investment wave, firms in Romania are combining energy storage with solar, wind and hydropower or building standalone systems

north macedonia guarantees of origin solar power plant oslomej

Good start for North Macedonia: in first two months 100k+ guarantees of origin issued

15 August 2025 - In April, the National Electricity Market Operator (MEMO) established the Register of Guarantees of Origin for electricity

serbia eps profit results 2025

Serbia’s EPS reports EUR 234 million profit for first half of 2025

15 August 2025 - State-owned Elektroprivreda Srbije (EPS) achieved lower profit in the first half of the year than in the same period of 2024

North Macedonia draft law envisages renewable energy auctions for CfDs

North Macedonia’s draft law envisages renewable energy auctions for CfDs

14 August 2025 - North Macedonia's draft Law on the Use of Energy from Renewable Sources covers auctions, CfDs, prosumers and renewable energy communities