PPC making progress with Mesochora hydropower, irrigation project

PPC progress Mesochora hydropower irrigation

Photo: Scheuerslow / https://creativecommons.org/licenses/by-sa/4.0/legalcode

Published

September 23, 2022

Country

Comments

comments icon

0

Share

Published:

September 23, 2022

Country:

Comments:

comments icon

0

Share

The environmental impact study for the 161.6 MW Mesochora hydropower plant in Greece is finished and the expropriation procedure is advancing rapidly, according to a news report.

The construction of the Mesochora dam in the Trikala region in the central part of Greece began 36 years ago, with a plan to divert the Acheloos (Achelous) river and build an irrigation system, which dates back to 1920.

The structure was almost finished in 2001, when the project was essentially suspended. The Council of State, the country’s supreme administrative court blocked it several times and there were also issues with the European Union.

Environmentalists and the affected communities have warned the reservoir, the diversion of the Achelous and the planned irrigation system would dry up the protected Messolonghi lagoon in the river’s delta. Locals also refused to relocate under the proposed terms.

PPC said it would need to invest EUR 81.4 million to finish the Mesochora project

Public Power Corp. (PPC or DEI) said in its last financial report that it has invested EUR 282 million so far. The government declared Mesochora a priority late last year. The environmental impact study for the hydropower project is now finished, Ot.gr reported without identifying sources and said it learned that the expropriation procedure for the diversion of the river is making rapid progress.

Overall works are valued at EUR 500 million in total since planning began, the article adds.

PPC estimated in early September that it can push forward the estimated start of operation by one year to the last quarter of 2025. The power utility said it would need to invest EUR 81.4 million more including the costs of relocating the people from the affected area.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

montenegro italy admir sahmanovic subsea cable solar wind

4 GW of solar, wind projects in pipeline in Montenegro – minister

04 April 2025 - Speaking at the Economic Dialogue Montenegro-Italy round table, minister Admir Šahmanović called for stronger cooperation between the two countries

Share coal power Finland nearly zero cogeneration plant shuts down

Share of coal power in Finland nearly zero as cogeneration plant shuts down

03 April 2025 - The now closed Salmisaari coal plant accounted for just 0.8% of the electricity mix in Finland together with three remaining ones

solar nuclear power prices europe eurelectric

Solar, nuclear lower Europe’s power prices by 30% in March

03 April 2025 - Solar broke a record in power generation in March for the third consecutive month, making up more than 10% of Europe’s electricity mix, Eurelectric said

PPC announces 5.8 billion plan for Western Macedonia, focused on photovoltaics, storage and data centers

PPC plans EUR 5.8 billion makeover of Western Macedonia coal region, including data centers

03 April 2025 - PPC presented a EUR 5.8 billion investment plan for the coal region of Western Macedonia in northern Greece