The fate of the 225 MW thermal power plant (TPP) Pljevlja, which accounts for 40% of Montenegro’s electricity production, remains uncertain. The whole situation boils down to the question of whether it is economically justified to invest in a thermal power plant in the era of decarbonization, but it could also be seen as a harbinger of what may happen to power plants across the region. TPP Pljevlja is in this situation because it’s the first of five power plants in Bosnia and Herezegovina, Montenegro, and Serbia to use up its 20,000 operating hours allowed under the opt-out mechanism.

The Energy Community Contracting Parties have accepted the opt-out mechanism in order to meet their obligation to apply the EU’s Large Combustion Plant Directive (LCPD), whose aim is to reduce air pollution and greenhouse gas emissions. The mechanism provides an additional time period for thermal power plant operators to modernize their facilities in line with EU standards or to prepare for their shutdown.

If a power plant has not been modernized to meet the LCPD standards by the time it uses up the 20,000 operating hours, then it must be closed.

TPP Pljevlja has used up its limit, while state power utility Elektroprivreda Crne Gore (EPCG) has signed an agreement on an environmental overhaul which is expected to bring the plant into line with the LCPD and enable it to continue to operate. However, works have not been launched yet, even though 15 months has passed since the agreement was signed. This can partly be justified by the COVID-19 pandemic, but the Montenegrin authorities have now started doubting that the planned overhaul would be economically justified given that the country intends to phase out coal by 2030. On the other hand, EPCG has repeatedly warned that the cost of delays in overhauling the power plant would be too high – as much as EUR 1 billion over a 10-year period.

Why is the environmental overhaul being delayed?

An answer provided by EPCG under the law on access to public information to non-governmental organization ASP suggests that works at TPP Pljevlja have not yet been launched, even though 15 months has passed since the agreement was signed.

ASP said in a statement that the contractor – a consortium led by China’s Donfang Electric International Corporation – is asking to be paid an additional EUR 15 million for the job, which, if completed, could turn out to be in vain given that Montenegrin officials have recently said the power plant is likely to be shut down by 2030.

Perunović: would investing in an environmental overhaul pay off?

According to ASP, this situation has arisen because the country’s energy policy over the past years has favored the construction of a second unit at TPP Pljevlja, instead of shifting to renewable sources. The non-governmental organization has also called on authorities to work out, as soon as possible, legal and economic alternatives for residents of the city of Pljevlja, as part of a just energy transition.

Reservations about the overhaul plan within the Montenegrin government are evident – as confirmed recently by Marko Perunović, a state secretary at the Ministry of Capital Investment.

He said that the government is looking for a solution which must include an environmental overhaul that will cost some EUR 15 million more than the projected EUR 54 million. The question is, according to him, would such an investment pay off?

EPCG: an environmental overhaul would pay off

An environmental overhaul, according to EPCG, is a prerequisite for the further operation of TPP Pljevlja, in terms of meeting environmental standards as prescribed by national and European regulations, primarily the LCPD and the Industrial Emissions Directive (IED), and Montenegro’s law on industrial emissions.

Abandoning the environmental overhaul project would inevitably lead to TPP Pljevlja’s closure, according to EPCG.

An environmental overhaul would be economically justified even with a 2030 deadline for TPP Pljevlja’s closure

The proposed works, worth EUR 15 million, are not related to members of the consortium, BB Solar and Bemax, EPCG said, adding that those are specialist works on reconstructing the boiler facility that are expected to be performed by a renowned international contractor.

Suspending the operation of TPP Pljevlja for 12 months would generate EUR 158 million in expenditures (EUR 109 million for electricity imports and EUR 49 million in fixed expenses), while an 18-month suspension would cost EUR 234 million (EUR 160 million for electricity imports and EUR 74 million in fixed expenses). These expenses, even in a short term, would exceed the cost of an environmental overhaul many times over. In a longer term, over a period of 10 years, the costs would exceed EUR 1 billion. This clearly demonstrates the gravity of the problem – economically, socially, and in terms of energy supply – that Montenegro will face if TPP Pljevlja is closed soon or if the environmental overhaul plans are abandoned, according to EPCG.

Even with a 2030 deadline for TPP Pljevlja’s shutdown (although EPCG believes the plant should be closed in the period between 2035 and 2040), the environmental overhaul project would pay off, the company claims.

Is there a solution?

The Montenegrin government is indeed considering alternative solutions. Prime Minister Zdravko Krivokapić has recently said that building a gas-fired power plant near the city of Bar is also an option.

Nebojša Medojević, leader of the Movement for Changes (PzP), regularly comments on the issue of TPP Pljevlja. A few days ago, he said that EPCG should immediately break off the environmental overhaul agreement, particularly because the contractors have failed to meet the deadlines and because a completion of the project would not help meet the envisaged standards.

Instead, according to him, EPCG should pursue alternative solutions that would be sustainable and efficient, both economically and in terms of energy.

Taxes that will be levied on coal will make lignite-based electricity generation unprofitable

His recommendation is to prepare a buyout program for TPP Pljevlja employees, including severance payments and options for finding another job or starting a small business. When it comes to the city of Pljevlja, it is necessary to work out alternative solutions, such as a biomass power plant, smaller hydropower plants, food production, or an environmentally-friendly cement factory outside of the city.

With all the taxes that will be levied on coal, according to him, producing electricity from lignite will simply become unprofitable.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

croatia geothermal energy soyak power plant legrad 1

Soyak to install 80 MW geothermal power plant in Croatia

25 December 2024 - Croatia has only one geothermal power plant - the 16.5 MW Velika 1 in Ciglena near Bjelovar

Energy Community pace of integration implementation EU steady but CBAM looms

Energy Community’s EU integration pace steady but CBAM looms

25 December 2024 - Energy Community contracting parties showed a tendency this year toward steady transposition and implementation of European law

Romania calls agricultural food firms apply solar wind power grants

Romania calls agricultural, food firms to apply for solar, wind power grants

25 December 2024 - The Agency for Financing Rural Investments (AFIR) has EUR 150 million in grants for photovoltaic and wind power in Romania

republic of srpska gacko ugljevik coal power

Republic of Srpska doesn’t have EUR 357 million to maintain production in coal power plants

24 December 2024 - Minister Petar Đokić held a meeting with the boards of directors and supervisory boards of coal complexes Gacko and Ugljevik