Ministry’s assessment for wind park annulled

Published

January 15, 2016

Comments

comments icon

0

Share

Published:

January 15, 2016

Comments:

comments icon

0

Share

The Administrative Court in Split accepted Association BIOM’s law suit and declared invalid the decision of Croatia’s Ministry of Environmental and Nature Protection to accept the construction of Bila Ploča wind power plant in Pelješac peninsula in the country’s south. This is the first ruling which blocks a project in an area significant for bird protection as it has been determined that the environmental impact assessment study was unfounded, BIOM said. According to its press release, studies have been produced unprofessionally for years, including findings related to the Natura 2000 network.

The process was initiated by the association and the Croatian Society for Bird and Nature Protection three years ago and the court issued the ruling on December 28. The situation with the study was absurd as state institutions had identified the area as significant for bird protection on an international level, said Vedran Lucić, spokesman of BIOM, and added that bad positioning of wind power plants can cause high mortality of birds and bats, as they collide with turbine blades.

Unfounded studies are the consequence of direct deals between investors and producers of the document, and the ministry tolerates actions against protected species and habitats in Croatia, the press release said. BIOM has three more pending law suits related to bird protection, for wind parks in the mountains of Dinara and Velebit.

Related Articles

eu region ministerial council 2025 meeting vienna

Serbia is first Energy Community contracting party to enter verification phase of market coupling

18 December 2025 - At the Energy Community Ministerial Council, ministers adressed energy security, market integration, climate policy and environmental protection

just transition coal region sostanj

Slovenia earmarks EUR 282.2 million for just transition, renewables in coal region

18 December 2025 - The plan envisages renewable energy projects in the district heating system and at the Šoštanj thermal power plant site

Enery obtains financing for 600 MWh battery project in Bulgaria

Enery obtains financing for 600 MWh battery project in Bulgaria

18 December 2025 - Austria-based Enery intends to commission a four-hour battery storage system of 150 MW in central Bulgaria by the end of March

Applications open first wind power auction Kosovo

Applications open for first wind power auction in Kosovo*

18 December 2025 - The Ministry of Economy of Kosovo* invited the three prequalified entities to submit bids for a wind power auction for up to 100 MW