The Administrative Court in Split accepted Association BIOM’s law suit and declared invalid the decision of Croatia’s Ministry of Environmental and Nature Protection to accept the construction of Bila Ploča wind power plant in Pelješac peninsula in the country’s south. This is the first ruling which blocks a project in an area significant for bird protection as it has been determined that the environmental impact assessment study was unfounded, BIOM said. According to its press release, studies have been produced unprofessionally for years, including findings related to the Natura 2000 network.

The process was initiated by the association and the Croatian Society for Bird and Nature Protection three years ago and the court issued the ruling on December 28. The situation with the study was absurd as state institutions had identified the area as significant for bird protection on an international level, said Vedran Lucić, spokesman of BIOM, and added that bad positioning of wind power plants can cause high mortality of birds and bats, as they collide with turbine blades.

Unfounded studies are the consequence of direct deals between investors and producers of the document, and the ministry tolerates actions against protected species and habitats in Croatia, the press release said. BIOM has three more pending law suits related to bird protection, for wind parks in the mountains of Dinara and Velebit.

Related Articles

croatia batteries BESS hgk position paper issues necp aljosa pleic

HGK: Croatia has only 11 MW of battery power, regulations stall investments

10 March 2026 - The Croatian Chamber of Economy (HGK) has published a position paper on barriers to battery investments in the country

epcg battery energy storage tender

No bids in Montenegro’s second tender for battery energy storage

10 March 2026 - The tender was for only 200 kWh to 260 kWh of battery storage, whereas the previous, cancelled bidding envisaged 240 MWh

montenegro cges s2p electric grid connection solar tupan prentic asanovic

Swiss S2P Electric signs grid connection deal for solar project in Montenegro

10 March 2026 - The contract represents the eighth such deal for grid connection for renewable energy power plants signed by Montenegro’s TSO CGES

Threat mass exodus desalination plants bombed in Iran Gulf countries

Threat of mass exodus as desalination plants targeted in Gulf countries, Iran

09 March 2026 - The Iran war could heavily disrupt the water supply in the region, and desalination plants in particular, alongside environmental disasters