Electricity

HSE, TEŠ receive EUR 261 million settlement from GE for TEŠ unit 6

hse tes ge settlement alstom unit 6

Photo: The HSE team involved in settlement (photo: HSE)

Published

March 15, 2021

Country

Comments

comments icon

0

Share

Published:

March 15, 2021

Country:

Comments:

comments icon

0

Share

Holding Slovenske Elektrarne (HSE) and Termoelektrarna Šoštanj (TEŠ) have signed an out-of-court settlement with General Electric (GE) worth a total of EUR 261 million in favour of TEŠ. The deal is related to Alstom Power’s involvement in the construction of TEŠ unit 6. GE acquired Alstom’s power businesses in 2015.

Holding Slovenske elektrarne and its subsidiary, the operator of the Šoštanj thermal power plant, submitted a request on January 25, 2017, for arbitration against GE before the International Chamber of Commerce over Alstom Power’s involvement in the investment in unit 6 of TEŠ in 2008.

The purpose of the arbitration was to reclaim alleged damages resulting from the construction of unit 6

The purpose of the arbitration was to reclaim alleged damages resulting from the construction of unit 6, HSE Group said in a press release.

After more than three years of intensive work, the two sides reached a EUR 261 million settlement agreement.

The agreement includes payment in the amount of EUR 138.7 million

The agreement includes payment in the amount of EUR 138.7 million, services worth EUR 10 million and around EUR 12 million in other savings and cost reimbursements.

As the settlement is related to the commercial claim made by HSE and TEŠ in arbitration, both companies have withdrawn the statement of claim in return for the compensation in the arbitration procedure and renounced further damages claims in arbitration. The condition for the withdrawal of the arbitration and renouncement of the claim was fulfilled with the transfer of the first installment of the funds in the amount of EUR 131 million to TEŠ’s bank account, HSE Group said.

Services worth EUR 10 million include long-term maintenance and digitalization of unit 6

Services worth EUR 10 million include long-term maintenance and digitalization of unit 6 with the objective to get advanced maintenance of the key technical equipment of unit 6 and the positive effects of the increase in availability and efficiency.

Other savings and reimbursement of costs that HSE or TEŠ would otherwise incur for the operation of unit 6 or other related activities.

Tags: ,
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

world energy crisis war renewables boom Simon Stiell un

Energy crisis fueled by Iran war makes economic logic of renewables impossible to ignore

04 May 2026 - The energy crisis fueled by the Iran war has made the economic logic of renewables impossible to ignore, according to Simon Stiell

Premier Energy building one of largest battery systems in Southeastern Europe

Premier Energy building one of largest battery systems in Southeastern Europe

04 May 2026 - Premier Energy Group has begun the construction of a 200 MW / 400 MWh battery energy storage system (BESS) in eastern Romania

nuclearelectrica us exim loan cernavoda expansion_cr

US export bank signs USD 57.3 million loan to back Romania’s nuclear plant expansion

04 May 2026 - The Export-Import Bank of the United States has signed a loan for engineering and project management services for two new reactors at the Cernavodă plant

energy community regulatory board evaluation report peci list projects

Six Projects of Energy Community Interest advancing without systemic delays

04 May 2026 - The Evaluation Report on PECI is providing an overview of the implementation progress of projects included in the 2024 PECI list