Funds raised for Croatia’s first renewable energy crowdfunding project

Funds raised for Croatia’s first renewable energy crowdfunding project

Slika: facebook/zelenaenergetskazadruga

Published

May 28, 2018

Country

Comments

comments icon

0

Share

Published:

May 28, 2018

Country:

Comments:

comments icon

0

Share

A 30 kW solar power plant will be built in early autumn on the roof of the Development Center and Technology Park owned by the Croatian City of Križevci, under the country’s first such crowdfunding project financed through micro loans.

The commissioning of the plant in an estimated investment of HRK 230,000 (EUR 27,000) is scheduled no later than September 30, after 100% of the funding was raised a few days ago, according to the website of Zelena Energetska Zadruga (ZEZ), which leads the crowdfunding project.

Some 50 people and several associations and small businesses recognized a good opportunity for investment, protecting the environment and fostering solar energy use, Croatian media reported. ZEZ representatives said that citizens were willing to invest twice as much as needed, and it is possible there will be similar projects very soon.

After ZEZ and the City of Križevci signed the contract on the promotion of the first crowdfunding project in the renewable energy sector in Croatia, ZEZ successfully finished the campaign entitled Križevački sunčani krovovi in just ten days. The solar rooftop project was created in cooperation with ZEZ, the City of Križevci and the Križevci Entrepreneurship Center (KPC).

Citizens were offered to invest money in a solar power plant by providing a 10-year loan with a 4.5% annual interest rate.

KPC, as the beneficiary of the administrative building of the Development Center, will install the photovoltaic power plant owned by ZEZ, which will generate electricity for its needs, while the surplus will be exported to the grid, according to ZEZ website.

The amount earned through the sale of surplus electricity would be used to repay the loans to investors.

The estimated CO2 emissions cut is 412,500 tonnes over a ten-year use of the plant.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

croatia batteries BESS study res croatia converence solar flex

Study maps 22 priority locations for BESS in Croatia

19 March 2026 - The national study identifies grid congestion locations and the need for battery energy storage systems in Croatia

photovoltaics in solar power station energy from natural. Close-up.

UniCredit Bank issues first green mini bonds in Serbia

19 March 2026 - UniCredit Bank acted as arranger and investor for the first green mini bond issuance on the domestic market in Serbia

slovenia eles solar power plants 2025

Slovenia’s solar capacity surges to 1.65 GW

19 March 2026 - Nearly 70,000 solar power units were on the grid in Slovenia in 2025, with a total installed capacity of 1,650 MW

Alive Capital Sieyuan Electric 2 5 GWh of battery storage

Alive Capital, Sieyuan Electric to deploy up to 2.5 GWh of battery storage

19 March 2026 - Alive Capital signed a deal with energy equipment manufacturer Sieyuan Electric for the deployment of battery energy storage systems