Funds raised for Croatia’s first renewable energy crowdfunding project

Funds raised for Croatia’s first renewable energy crowdfunding project

Slika: facebook/zelenaenergetskazadruga

Published

May 28, 2018

Country

Comments

comments icon

0

Share

Published:

May 28, 2018

Country:

Comments:

comments icon

0

Share

A 30 kW solar power plant will be built in early autumn on the roof of the Development Center and Technology Park owned by the Croatian City of Križevci, under the country’s first such crowdfunding project financed through micro loans.

The commissioning of the plant in an estimated investment of HRK 230,000 (EUR 27,000) is scheduled no later than September 30, after 100% of the funding was raised a few days ago, according to the website of Zelena Energetska Zadruga (ZEZ), which leads the crowdfunding project.

Some 50 people and several associations and small businesses recognized a good opportunity for investment, protecting the environment and fostering solar energy use, Croatian media reported. ZEZ representatives said that citizens were willing to invest twice as much as needed, and it is possible there will be similar projects very soon.

After ZEZ and the City of Križevci signed the contract on the promotion of the first crowdfunding project in the renewable energy sector in Croatia, ZEZ successfully finished the campaign entitled Križevački sunčani krovovi in just ten days. The solar rooftop project was created in cooperation with ZEZ, the City of Križevci and the Križevci Entrepreneurship Center (KPC).

Citizens were offered to invest money in a solar power plant by providing a 10-year loan with a 4.5% annual interest rate.

KPC, as the beneficiary of the administrative building of the Development Center, will install the photovoltaic power plant owned by ZEZ, which will generate electricity for its needs, while the surplus will be exported to the grid, according to ZEZ website.

The amount earned through the sale of surplus electricity would be used to repay the loans to investors.

The estimated CO2 emissions cut is 412,500 tonnes over a ten-year use of the plant.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Romania preparing to build giant AI hub data centers

Romania preparing to build giant AI hub, data centers

29 January 2026 - Romania is developing its Black Sea AI Gigafactory project, of up to EUR 5 billion, and several other investments in new technologies

montenegro TNC eco team mapping low-conflict solar wind potential

Montenegro identifies 16.3 GW of low-conflict solar and wind potential

29 January 2026 - The Montenegro Energy Growth and Acceleration project was implemented by The Nature Conservancy and Montenegrin NGO Eco-Team

Record battery installations EU 2025 Bulgaria enters top 3

Record battery installations in EU in 2025 as Bulgaria enters top 3

28 January 2026 - The European Union added 27.1 GWh of battery capacity last year, marking a 12th consecutive record – driven by utility-scale storage

croatia ante susnjar minister renewables subsidies jutarnji list energy conference

Šušnjar: Croatia allocated EUR 4 billion so far to boost renewables; subsidies for wind, solar to end

28 January 2026 - Minister of Economy Ante Šušnjar said at an energy conference that the money could have been put to better use