A 30 kW solar power plant will be built in early autumn on the roof of the Development Center and Technology Park owned by the Croatian City of Križevci, under the country’s first such crowdfunding project financed through micro loans.

The commissioning of the plant in an estimated investment of HRK 230,000 (EUR 27,000) is scheduled no later than September 30, after 100% of the funding was raised a few days ago, according to the website of Zelena Energetska Zadruga (ZEZ), which leads the crowdfunding project.

Some 50 people and several associations and small businesses recognized a good opportunity for investment, protecting the environment and fostering solar energy use, Croatian media reported. ZEZ representatives said that citizens were willing to invest twice as much as needed, and it is possible there will be similar projects very soon.

After ZEZ and the City of Križevci signed the contract on the promotion of the first crowdfunding project in the renewable energy sector in Croatia, ZEZ successfully finished the campaign entitled Križevački sunčani krovovi in just ten days. The solar rooftop project was created in cooperation with ZEZ, the City of Križevci and the Križevci Entrepreneurship Center (KPC).

Citizens were offered to invest money in a solar power plant by providing a 10-year loan with a 4.5% annual interest rate.

KPC, as the beneficiary of the administrative building of the Development Center, will install the photovoltaic power plant owned by ZEZ, which will generate electricity for its needs, while the surplus will be exported to the grid, according to ZEZ website.

The amount earned through the sale of surplus electricity would be used to repay the loans to investors.

The estimated CO2 emissions cut is 412,500 tonnes over a ten-year use of the plant.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Montenegro Ministerial Energy Forum Energy Investment Dialogue Berlin Process chairmanship

Montenegro hosts Ministerial Energy Forum, Energy Investment Dialogue within its Berlin Process chairmanship

23 April 2026 - As part of its chairmanship of the Berlin Process, Montenegro today hosted the Ministerial Energy Forum and the Energy Investment Dialogue

north macedonia blackout entso e final report

ENTSO-E final report: Overvoltage caused blackout in North Macedonia 

23 April 2026 - The final report was prepared by an 18-member Panel comprising representatives from TSOs, ACER, and national regulatory authorities

OMV Petrom Renovatio construction wind parks 305 MW Romania

OMV Petrom, Renovatio starting construction of wind parks totaling 305 MW in Romania

23 April 2026 - OMV Petrom and its partner RNV Infrastructure are entering the execution phase for three wind power projects of 305 MW in total

Bankwatch Western Balkans abandon waste to energy incineration

Bankwatch: Western Balkans must abandon waste-to-energy incineration

22 April 2026 - Plans for waste incinerators and co-incineration in the Western Balkans pose high financial and health risks, CEE Bankwatch Network warns