Evaluation of applications for HPP Dabar project to be repeated

Photo: Hidroelektrana Dabar

Published

July 26, 2019

Comments

comments icon

0

Share

Published:

July 26, 2019

Comments:

comments icon

0

Share

The evaluation of applications to bid for financing and building hydropower plant HPP Dabar will have to be repeated, after part of the procedure was annulled following a complaint filed by one of the applicants, a consortium of China National Electric Engineering Co. Ltd (CNEEC) and Slovenia’s RIKO, local media reported.

Bosnia and Herzegovina’s office handling complaints in public procurements has dismissed CNEEC and RIKO’s objections to their disqualification in the first phase of the procedure to select a partner for HPP Dabar, but it has accepted their claim that the other participants have also failed to prove they possess the required personnel capacities, according to reports.

In January this year, Hidroelektrana Dabar, a subsidiary of hydropower plant operator Hidroelektrane na Trebišnjici (HET), a unit of Elektroprivreda Republike Srpske, issued a public call for financing and building HPP Dabar, a turnkey/engineering project valued at some EUR 200 million. The deadline to submit applications was March 1.

Two Chinese companies were cleared for the second phase on April 22, while the CNEEC-RIKO consortium was disqualified. The consortium then lodged a complaint, alleging that the tendering procedure was rigged, local media recalled.

“Irregular and unconvincing approach” in considering applications

In the explanation of its decision to order a repeat procedure, the complaints office said that Hidroelektrana Dabar, in the part of its decision referring to personnel capacities of two applicants, stated merely that the required information was “submitted,” which, in the office’s opinion, was an “irregular and unconvincing approach” in considering the applications.

Hidroelektrana Dabar was therefore ordered to repeat the evaluation procedure and prepare documentation that will contain the “necessary analytical elements” regarding the required and submitted evidence.

HPP Dabar is to be built on the Trebišnjica river, and its installed capacity is planned at 160 MW, according to earlier reports. Under the preferred financial model, the future partner would secure a loan to cover at least 85% of the project cost.

In late 2018, Hidroelektrana Dabar selected a consortium led by AF-Consult Switzerland Ltd. to advise it in awarding a contract to build the hydropower plant. The consortium also includes auditor Deloitte d.o.o. in Belgrade, Serbia and law firm Moravčević, Vojnović i Partneri AOD, also based in Belgrade.

HPP Dabar is one of the projects planned by power utility Elektroprivreda Republike Srpske over the next 10 years.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment

Related Articles

Zivkovic EPS BEF 2025 Weakness in Serbian energy system is no option

Weakness in Serbian energy system is no option

16 May 2025 - Serbia's EPS is committed to green targets, but it won't compromise energy security, CEO Dušan Živković said at BEF 2025

bih belgrade energy forum 2025 bef mirza kusljugic batteries

BiH laying groundwork for battery energy storage systems

15 May 2025 - The State Electricity Regulatory Commission is drafting a decision on BESS, Mirza Kušljugić said at Belgrade Energy Forum 2025

North Macedonia Law on Energy

North Macedonia adopts Law on Energy

15 May 2025 - With a majority of votes, 62 out of 120, the Assembly of North Macedonia adopted the Law on Energy, aligning the legal framework with the EU

Consortium completing spatial plan for solar-BESS strategic partnership in Serbia

15 May 2025 - Hyundai Engineering and UGT Renewables are in a strategic partnership in Serbia for 1.2 GW, with batteries. They plan to expand in the region.