Electricity

Energy crisis accelerates construction of Bistrica pumped storage hydropower

Bistrica pumped storage HPP project

HPP Potpeć (photo: EPS)

Published

May 23, 2022

Country

Comments

comments icon

0

Share

Published:

May 23, 2022

Country:

Comments:

comments icon

0

Share

Serbia has taken two essential steps in preparation for constructing the pumped storage hydropower plant Bistrica. It is one of the most critical investments in the energy sector of Serbia, with a projected capacity of 630 megawatts (MW).

State-owned power utility Elektroprivreda Srbije (EPS) has chosen the companies that will prepare a preliminary design and feasibility study for the Bistrica project, and the Government of Serbia has decided to develop a spatial plan for the special purpose area for ​​the pumped storage hydropower facility Bistrica and the Potpeć hydropower plant.

The plan for the construction of Bistrica dates back four decades. The project has become more relevant in recent years because Serbia needs new production capacities, especially those for storing energy and balancing intermittent production from wind farms and solar power plants. This way, the country also creates conditions for investments in renewables.

In the meantime, the energy crisis started and pushed electricity prices to record levels. On top of that, EPS experienced a collapse in coal and electricity output in December last year. Since then, Serbia can’t produce enough electricity for its needs, making imports worth hundreds of millions of euros inevitable. The crisis in electricity production caused decision-makers to accelerate the decision on the construction of new power plants.

Energoprojekt Hidroinženjering is responsible for the design

EPS launched a tender in December to develop the preliminary design and feasibility study for the construction of Bistrica pumped storage. The job was awarded to a local consortium of Energoprojekt Hidroinženjering, EKC, and the Institute of Architecture and Urban and Spatial Planning of Serbia.

Their offer was the only one received in time and acceptable, with the price of EUR 1.6 million excluding VAT, EPS said.

The deadline for drafting the design is 18 months

The deadline to prepare a preliminary design and feasibility study is 18 months. Interestingly, Energoprojekt Hidroinženjering delivered the first design back in 1981.

The second important step is preparing the spatial plan for the special purpose area for Bistrica hydropower pumped storage and the Potpeć hydropower plant. The second power plant has already been built and has been operating with a capacity of 60 MW since 1967 as part of EPS.

According to the government’s decision, the plan includes parts of the municipalities of Nova Varoš, Priboj, and Prijepolje. The deadline for preparing it is 12 months, and EPS will provide the funds.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Dama Solar rezolv in Romania expanded to become Europe's biggest PV project

Dama Solar in Romania expanded to become Europe’s biggest PV project

23 March 2026 - With its 1.3 GW, Rezolv Energy's Dama Solar would be the biggest photovoltaic plant in Europe, excluding Turkey

romania nuvve omnia bess battery brasov

Nuvve Holding, Swiss Omnia Global to install 120 MWh BESS in Romania

20 March 2026 - The BESS project in Braşov, a city in central Romania, is the third in Europe under a cooperation agreement of Nuvve Holding and Omnia Global

IEA urges demand-side measures to ease energy crisis from Iran war

IEA urges demand-side measures to ease energy crisis from Iran war

20 March 2026 - The escalating energy crisis from the Iran war can be eased with a range of demand-side measures spanning transportation, cooking and industrial production

energy community ecrb report electricity network tariffs

ECRB report maps reforms to modernize Energy Community electricity network tariffs 

20 March 2026 - The Energy Community Regulatory Board (ECRB) has released its 2025 Best Practice Report on electricity network tariff methodologies