The European Bank for Reconstruction and Development will conduct a final review of the project for the restructuring of Albanian Power Corporation (KESH sh. a.) and the energy sector of Albania in general with focus on sector management and operational efficiency. The international financing institution’s project summary document said loan proceeds will be used to refinance and lengthen the tenors of short-term sovereign guaranteed overdrafts which KESH has entered into with commercial banks on an emergency basis and require annual reapproval, perpetuating a liquidity crisis as well as uncertainty and instability.

The sovereign guaranteed loan of EUR 218 million will be divided into two tranches. Involvement of commercial banks for co-financing will be explored, mainly for the second tranche. The full amount of the proceeds will be applied to refinancing short-term debt.

The loans were necessary to alleviate critical cash shortages created by hydrology conditions and sector organization, the document adds. The reforms aim to include KESH’s corporate governance, market practices and regional trade. The refinancing of the balance sheet should lengthen tenors and relieve the utility of urgent liquidity concerns, EBRD stated.

The project supports both the bank’s policy dialogue efforts for reform in the sector as well as opportunities for the country to develop regional and internal market principles. The project will promote regional integration and trade. It will promote the adoption of secondary legislation consistent with and required for the implementation of the new Power Sector Law. This is expected to include improvements in tariff formation. The bank said it will also require a thorough corporate governance review and recommendations for how to bring KESH to best international standards in compliance with international norms and codes.

The state-owned electricity utility meets almost 70% of Albania’s electricity demand. Due to the general corporate nature of the project, the bank will review all operations of the company and review whether current investment plans allow KESH to attain European Union’s environmental standards, the document said. The potential impacts of the restructuring on workers (for example the risk of retrenchment) or on tariff affordability will need to be addressed, according to EBRD.

Related Articles

Serbia drafts just transition action plan public debate

Serbia drafts just transition action plan

30 May 2025 - The Ministry of Mining and Energy has published a draft just transition action plan and launched a public debate

Regional Power Sector Exchange Western Balkans disitribution system operator dso grids ohrid giz

Third Regional Power Sector Exchange in Ohrid: Power grids at core of energy transition

30 May 2025 - The third Regional Power Sector Exchange of the Western Balkans gathered over 80 energy professionals from the Western Balkans

Maja Maćić, Balkans Platform Head at Alcazar Energy

Maja Maćić: Alcazar Energy expands presence in Western Balkans

30 May 2025 - Maja Maćić, executive manager of Alcazar Energy, said at Belgrade Energy Forum that construction activities for some projects would start as early as this year

two solar power plants egesa enerji vojvodina

Turkish Egesa Enerji to build two solar power plants in Serbia’s Vojvodina province

30 May 2025 - Turkish company Egesa Enerji has launched a project to build two solar power plants in Vojvodina, with a total nominal capacity of 8.6 MW