CWP Global to build first utility-scale solar power plant in Serbia

CWP Global to build first utility-scale solar power plant in Serbia

Location of the solar power plant (photo: CWP Global)

Published

June 15, 2021

Country

Comments

comments icon

0

Share

Published:

June 15, 2021

Country:

Comments:

comments icon

0

Share

Renewable energy company CWP Global will start building a 50 MW solar power plant near the southwestern Serbian town of Sjenica at the beginning of 2023, in a EUR 40 million investment. The plant, called Kima Solar, will be the first large photovoltaic facility in Serbia, marking the beginning of the country’s solar boom.

The recent adoption of Serbia’s law on renewable energy sources has created conditions for an accelerated development of green energy projects, particularly photovoltaic power plants, given that the total installed solar capacity in the entire country is about 20 MW, while the potential is far greater.

The announcement of the project on the Pešter plateau confirms investors’ recent message that they have big plans for developing solar power plants in Serbia. In April this year, at the First Big Conference on Solar Energy in Serbia, organized by the Balkan Green Energy News portal, Maja Turković, Vice President of CWP Global for Serbia, said the country could get 1 GW of solar power plants by 2030.

The largest solar power plant in Serbia currently has a capacity of 2 MW, and the total installed capacity in the country is 20 MW

Nikola Stamenov, director of Kima Solar, a project company of CWP Global, has told Balkan Green Energy News that the project milestone was the Sjenica municipal assembly’s decision to approve the company’s initiative to change the relevant planning document and adopt a motion to start building the solar park.

“We are now entering the procedure of obtaining all the necessary permits and approvals to start construction. The launch of works is planned for the beginning of 2023, and the power plant should be online by the beginning of 2024. The 50 MW solar power plant on the Pešter plateau will be by far the biggest solar power plant in Serbia, given that the largest PV facility at the moment has a capacity of 2 MW. It will increase the country’s existing solar capacity by almost 150 percent,” Stamenov said.

CWP Global will sell electricity on the market

He says that the electricity produced at Kima Solar will be sold on the market, so the company does not expect any subsidies from the state. CWP Global will decide on taking part in the announced renewable energy auctions once their design and timeline are announced.

CWP is currently working on a project to develop the world’s largest power plant

CWP Global is one of the biggest investors in wind farms in Serbia, and has recently started developing solar projects as well. Including its capacities in Romania and Australia, CWP has to date delivered 1,525 MW of renewable energy capacity, with financing totaling EUR 3 billion, in what helped avoid emissions of 18.6 million tons of CO2.

In cooperation with partners, CWP is currently working on a project to develop the world’s largest power plant, called the Asian Renewable Energy Hub – a hybrid plant consisting of wind turbines and solar panels, along with the world’s biggest green hydrogen and green ammonia hub.

Sjenica, Pešter set to become clean energy hub on Europe’s energy map

Representatives of CWP Global and the municipality of Sjenica have recently met at the company’s headquarters in Belgrade to agree on further activities on the installation of the photovoltaic facility.

Maja Turković, Vice President of CWP Global for Serbia, has said that Kima Solar will supply green energy to more than 20,000 households. According to Turković, the power plant is not only significant for Serbia’s energy stability and its intention to support renewable energy projects, but is also of great importance for the development of the local community and the entire Pešter region.

The solar power plant will be located near ​​the village of Kamešnica

“We are excited to be able to jointly position Sjenica and Pešter as a center of clean energy on the energy map of Europe,” she added.

Rejhan R. Kurtović, president of the Sjenica municipal assembly, has said that further steps in the development of the project in the area of ​​the village of Kamešnica were agreed at the meeting, and that a team of managers from CWP Global has done a lot of work so far.

“The company has acquired privately-owned land on the territory of our municipality where the solar power plant will be built. It has also taken steps to obtain permits and secure all necessary conditions to start construction works, which is a prerequisite for the further development of this project and cooperation with the local authorities,” said Kurtović.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

DRI OMV Petrom Romania largest physical PPA

DRI, OMV Petrom sign Romania’s largest physical PPA so far

21 December 2024 - The new physical solar power purchase agreement between DRI and OMV Petrom is the largest ever in Romania

Renewable energy project frenzy in Greece defies curtailments, grid constraints

Renewable energy project frenzy in Greece defies curtailments

20 December 2024 - Applications for new renewable energy projects continued unabated in Greece in 2024 according to Independent Power Transmission Operator

croatia subsidies bih municipalities climate change

Croatia to grant EUR 5 million for climate action projects in BiH

20 December 2024 - The Ministry of Environmental Protection and Green Transition has issued a call for awarding funds for climate action projects

north macedonia esm kfw bogdanci bitola solar wind uncev Moritz Remé

North Macedonia’s ESM secures loan, grant for solar projects, wind farm Bogdanci

20 December 2024 - The solar power plants will be installed within coal mining and energy complexes REK Bitola and REK Oslomej