CEDIS to install additional 20,000 smart meters, boost coverage to 97%

CEDIS to install additional 20,000 smart meters - rollout reaches 97 percent

Published

August 3, 2022

Country

Comments

comments icon

0

Share

Published:

August 3, 2022

Country:

Comments:

comments icon

0

Share

The Montenegrin distribution system operator (DSO), Crnogorski elektrodistributivni sistem (CEDIS), has started the installation of 20,000 smart meters as part of a project to modernize electricity consumption metering and enable remote consumption management.

Since 2011, within its advanced metering management (AMM) project, worth EUR 100 million, CEDIS installed 338,000 meters and integrated them with the remote measurement and management system. It covered 81.5% of consumers on the distribution grid, which is more than most European countries.

With an additional 20,000 meters, smart meter coverage will reach almost 97%, given that CEDIS supplies 370,000 consumers. At the end of 2021, the average in the European Union was around 50%. Spain, Finland, and Sweden led the way with 100% coverage.

The AMM project was financed from a loan secured by the European Bank for Reconstruction and Development (EBRD), and partly from the company’s own funds.

The consortium Mezon-Regiocom will install 20,000 smart meters

The company completed the third phase in December 2020. CEDIS has signed the contract for the expansion of the third phase with the Mezon-Regiocom consortium.

In parallel, CEDIS said it would reconstruct the low-voltage network, the company said.

The third phase will include the reconstruction of measuring points and grid upgrades to support the new technology for remote consumption metering.

The basis of a smart grid

With the new system of remote metering, accuracy has been significantly increased, and the possibility of error has been reduced to a minimum, according to CEDIS.

The new meters enable monitoring of the voltage level of the grid, while consumers have access to real-time monitoring of consumption.

The project transformed the distribution grid into a modern and more energy-efficient network, CEDIS said.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

slovenia coal phaseout coal mine velenje golob robert visit

Slovenia begins preparations for closure of Velenje coal mine

09 October 2025 - Slovenian Prime Minister Robert Golob visited the Velenje coal mine to present a draft law on its gradual closure

Metlen Karatzis Greece largest battery joint venture

Karatzis, Metlen to install Greece’s largest battery in joint venture

09 October 2025 - Metlen and Karatzis Group of Companies are establishing a joint venture for a standalone BESS of 330 MW and 790 MWh

world dnv energy transition energy transition outlook 2025

Policy changes in US will have marginal impact on global energy transition

09 October 2025 - AI energy use may seem alarming, but it is projected to stay below EV charging and the cooling of buildings, DNV calculated

Bulgaria BEH direct link Black Sea cable participate project

Bulgaria’s BEH wants direct link to future Black Sea cable to participate in project

09 October 2025 - CEO of BEH Valentin Nikolov hinted that Bulgaria would opt for an electricity corridor via Turkey if the proposed cable under the Black Sea doesn't include a direct link to his country