Renewables

Coal power plant Maritsa East 3 plans to build solar plant, 200 MW battery system

maritsa east 3 coal power plant battery shtonov

Photo: ContourGlobal

Published

June 23, 2025

Country

Comments

comments icon

0

Share

Published:

June 23, 2025

Country:

Comments:

comments icon

0

Share

Coal-fired power plant ContourGlobal Maritsa East 3, which operates only sporadically to ensure the stability of supply for Bulgaria’s power system, plans to repurpose the grid infrastructure of its units 1 and 2 for solar and battery storage capacities. Units 3 and 4 will remain on standby to generate electricity during peak demand periods in the summer and winter months, but the plant will need state support to cover maintenance and workforce costs.

Maritsa East 3 (Maritsa iztok 3), majority owned by the US-based ContourGlobal, plans to use the existing grid infrastructure, including transformers and switchgear, to speed up the green energy project within the complex, according to Vassil Shtonov, Executive Director of ContourGlobal Bulgaria.

The central element is a 200 MW standalone battery energy storage system (BESS), the largest of its kind in Bulgaria, which would improve the flexibility and stability of the national power system, Shtonov explained in an interview with Capital.bg.

The project involves a 200 MW standalone battery system and a solar power plant

The planned battery system at Maritsa East 3 was among 82 projects selected to receive a total of EUR 587 million in subsidies from Bulgaria’s Ministry of Energy in April this year.

“In parallel, we are considering the development of an additional hybrid solar park with a battery at the same site,” he said. This will allow for faster deployment of new clean energy capacity, while preserving all options for future use of the coal-fired plant and its original infrastructure, Shtonov added.

ContourGlobal plans to build 400 MW to 500 MW of renewable energy capacity combined with batteries

ContourGlobal plans to invest hundreds of millions of euros to develop 400 MW to 500 MW of renewable energy capacity combined with storage systems, he said, adding that nearly half of this target is under construction or final approval. The company’s goal is to phase out coal by 2027 and achieve carbon neutrality by 2040, he stressed, recalling that Bulgaria’s targeted coal phaseout date is 2038.

Keeping coal plants on standby requires state support

Bulgaria’s state-owned National Electricity Co. (NEK) holds a minority stake in Maritsa East 3. After the plant’s 15-year power purchase contract with NEK expired in February 2024, it has only been able to operate on the free market for a few months a year. This year, units 3 and 4 were online from January to the end of March to maintain energy security.

Shtonov: Key coal-fired power plants should get a fixed amount from the state

However, to be on standby for system security, the plant needs to keep workers on the payroll even when it is not operating. For this reason, strategically important coal-fired power plants should receive a fixed amount from the state to cover ongoing personnel and maintenance costs, and then be switched on when necessary to protect consumers from sharp increases in electricity prices, as happened last year in July and November, according to Shtonov.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

ie energy bess smart battery storage

Croatian IE-Energy, Slovenia’s NGEN plan virtual network of smart battery storage systems

10 October 2025 - The EUR 60 million project is a step toward creating a virtual network of battery storage systems connecting renewable energy producers and consumers.

bih republic of srpska cbam petar djokic

Đokić: We expect EU to accept request to postpone CBAM implementation

10 October 2025 - Minister of Energy and Mining of the Republic of Srpska expressed belief that the European Commission would postpone the implementation CBAM

north macedonia batteries BESS solar wind natural gas investments sanja bozinovska

North Macedonia receives applications for 4.2 GW of battery projects

10 October 2025 - October 1 was the deadline for foreign investors interested in the construction of power plants to submit their initiatives

CJR Renewables 102 MW Urleasca wind farm Romania

CJR Renewables completes construction of 102 MW Urleasca wind farm in Romania

09 October 2025 - The Urleasca wind farm in Brăila county in eastern Romania is complete, contractor CJR Renewables said